Home  

Building Statistics

 

General Building Data: 

   
Building Name: William H. Gates Hall
   
Location & Site: University of Washington
  Northeast 43rd Street & 15th Avenue Northeast
  Seattle, WA
   
Building Occupant Name: University of Washington School of Law
   

Occupancy Type:

Educational
   
Size: 196,000 sq. ft.
   
Number of Stories: Above Grade: 4
  Total Levels: 6
   
Primary Project Team: Owner: University of Washington, Seattle Campus
  General Contractor: Lease Crutcher Lewis
  Construction Manager: Lease Crutcher Lewis
  Executive Architect: Mahlum Architects
  Design Architect: Kohn Pedersen Fox
  Design Architect: Kohn Pedersen Fox
  Structural/Civil Engineer: Magnusson Klemencic Associates
  Mechanical Engineer: CBG Consulting Engineers
  Electrical Engineer: Sparling
  Lighting Designer: Candela
  Landscape Architect: Murase Associates
  Acoustical Engineer: The Greenbusch Group
  Testing & Inspections: Mayes Testing Engineers
  Geotechnical Engineer: GeoEngineers
   
Dates Of Construction: July 30, 2001 – July 18, 2003
   
Cost Information: Total Project Cost: $82,679,787
 

Consultant Services: $8,166212

 

Construction: $63,432,789

 

Equipment: $8,202,506

 

Project Management: $1,807,112

 

Other: $1,071,166

   

Project Delivery Method:

Design-Bid-Build
   
 Architecture:  

Located on the northwest corner of the campus, the William H. Gates Hall provides a new home for the UW School of Law, bringing all the faculty and students under one roof for the first time in twenty years.  Built on what previously was a parking lot, Gates Hall creates a strong presence at the 43rd St pedestrian corridor, linking to the campus’ main entrance at Memorial Drive. The196,000 square foot building houses offices, lecture halls, classrooms, courtrooms, student commons and the Northwest's finest law library. Four soaring architectural skylights in the southwest plaza provide daylight to the law library and puncture onto the outdoor terrace that sits atop the library, giving the law school a distinguishing appearance.

William H. Gates Hall is designed and centered around the Marian Gould Gallagher Law Library, which is symbolically located at the “foundation” of the building.  Providing 40,000 square feet of book stacks and 10,000 square feet of reading room, the Marian Gould Gallagher Law Library sits two floors below grade and is encapsulated by the terrace above and the main L-shaped structure on its north and west sides. With the four trapezoidal sky lights connecting the library to the outside world, the central terrace provides an outdoor gathering place for students and faculty. Linking the main structure and the terrace is a glazed two-story galleria, which serves as the main circulation corridor for building.  The daylight infused Brotman Galleria provides access to classrooms and seminar rooms on the first and second floors. The main entrance of the building is located at the east end of the building, along Memorial drive and feeds into a double-height lobby.  The modest “grand” staircase in the lobby provides access to the library below and the pro-bono law offices above. While the first two levels of the building primarily house courtrooms, classrooms and seminar rooms, the upper two levels accommodate mostly faculty and administrative offices. 

   
Major Nation Model 1997 Uniform Building Code with City of Seattle Amendments
Codes: National Fire Protection Association Codes
  National Electric Code (NFPA 70, 1996)
Local Codes: 1997 Seattle Building Code
  1997 Washington State Building Code
  1997 Washington State Energy Code
  Washington State Electrical Code
  Seattle Electrical Code
   
Zoning:  
Building will following zoning designation 105-MR. Zoning of UW campus is Major Institution Overlay (MIO), and development within this area is governed by regulations set forth in the Development Standards of the University Master Plan.
   
Historical Requirements of zone where built:
Site of building was formerly a parking lot.
   
Building Envelope:  

The exterior walls of William H. Gates Hall are predominantly brick and glazed aluminum. The north and west facades of the building are mostly laid-in-place brick veneer over CMU backing wall, following the standard University of Washington barrier wall system. A Norman 2-3/4 by 12 brick module is used in a combination of colors to complement the campus’ existing brick color palette. The South and East facades, including the entry lobby, gallery overlooking the terrace, and the perimeter walls of the library utilize a glazed aluminum curtain wall system. The stair wells and upper levels of the South facing perimeters use a glazed aluminum curtain wall with a different mullion pattern. Standard glazing throughout the building is insulated glazing units with low-E performance glass.

The main roofing system consist of standing seam roofing over insulation, supported on a 3” metal roof deck, which spans horizontally between steel beams that are parallel to the ridge.  The lower, flat roof levels consist of gravel ballast over waterproofing membrane and insulation, also supported on 3” metal roof deck, supported by steel beams and girders.

   
   
Primary Engineering Systems 
   
Construction:  
Construction of William H. Gates Hall began in July 2001. Following a dedication ceremony, the building was opened to the public on September 12, 2003. The general contractor/construction manager (GC/CM) for the project was Lease Crutcher Lewis.  By using GC/CM contracting approach for this job, Lewis was brought aboard early in design and helped provide a detailed analysis at every step of the project. 
   
Electrical:  
William H. Gates Hall utilizes a radial system, in which the service is brought to the building through two 13.8 kV primary feeders tapped from the main campus distribution system.  These two feeders enter the building in the Main Electric Room on level L2 and are connected to the three-bay primary switchgear.  This then feeds a single-ended interior substation and the primary switch, which is rated at 15KV, 600 amperes, 500MVA short circuit duty, serves a 2500/3333 KVA fan cooled, dry type transformer.  The secondary serving voltage for the building is a 480Y/277 volts, 3 phase, 4 wire grounded Wye system.  The majority of the building’s mechanical system and lighting loads are served at these voltages, and 120 and 208 volt loads are served through additional step-down transformers.  The 4000 ampere bus in the main power center is protected by a 4000 ampere main circuit breaker.  This power center further feeds two 215 KW chillers, a 400 A automatic transfer switch for emergency power, a 400 A elevator distribution panel, a 1600 A distribution panel, and five 480:208Y/120 volt dry type transformers.
   
Lighting:  

In efforts to achieve desired design goals, the lighting throughout William H. Gales Hall primarily utilizes fluorescent lighting.  Classrooms and seminar rooms make use of suspended indirect/direct fluorescent luminaires, as do the majority of the offices spaces, while the courtroom spaces uses primarily compact fluorescent downlighting.  The circulation corridors also take advantage of compact fluorescent downlighting, as well as linear fluorescent wallwashers.  Several areas make use of metal halide luminaires, primarily in the form of track fixtures and downlights. 

Daylighting is utilized in several of the spaces, most noticeable the galleria corridor which runs through the heart of the building. The two story galleria is lined on one side by a two story glazed curtain wall. Daylighting is also incorporated in the library by four large skylights which protrude through to the terrace above.

   
Structural:  

The primary floor structural system consists of 34’6” by 34’6” composite bays with 3 ½” concrete slab on 3”metal decking and steel beams and girders. The foundation system is composed of spread footings with 1’-4” foundation walls. The system is supported laterally by concrete shear walls, varying between 12” to 14” thick, with two layers of reinforcement.

   
Mechanical:  

The University of Washington is served by a network of underground utilities, from which low pressure steam is extended to the building.  The steam, steam condensate and compressed air enter William H. Gates Hall at Level L2 in the northeast corner of the building. Both domestic hot water and space heating are provided from this steam throughout the entire building.

Located on the top level (Level 4) in the fan room are nine air handling units with capacities ranging between 10,080 and 29,940 cfm. Air is distributed throughout the building by means of fan-powered terminal boxes with water source reheat coils.

The cooling utility is provided throughout the building my means of two 275 ton centrifugal chillers and two 59,850 cfm cooling towers.
   
Fire Protection:  

William H. Gates Hall is fully sprinklered and utilizes a multiplexed, analog addressable, annunciate, electrically supervised fire alarm system.  Complying with University of Washington Facility Design Information Standards, as well as the Seattle Fire Code and ADA, the building contains all necessary fire alarm equipment and controls, including smoke detection in many public areas and HVAC supply and return plenums, pull stations, combination speaker/visual fire alarm devices, door releases, sprinkler system flow switches and fan shutdown circuitry.

   
Telecommunications:  

A complete voice, data, and multimedia communications infrastructure system is provided throughout William H. Gates Hall.  Student seating areas in classrooms are provided with underfloor raceway stub-ups and connections to multi-outlet assemblies for future use.  In addition to this, flush floor junction boxes are placed at selected locations in the floor for access from podiums and future fixed arrangements.

There are various communications systems and related equipment located throughout the building. These include, but are not limited to: wireless access points mounted in the ceilings of all classrooms, seminar rooms and court rooms; communications receptacle outlets all throughout the building for phone and data connections; several cable television outlets; and data/video projector and recorder outlets.

   
Transportation:  

There are three stairwells located at the NE, NW and SW corners of the building which serve as the primary means of transportation throughout the building. In addition to this, there are two additional stairways which serve the main level and two below grade levels for access to and from the library.  There are also four elevators located throughout the building. One elevator is located in the library and serves only the two below grade library levels. The three remaining elevators serve the entire building, with two elevators located at the northeast corner of the building right off of the main lobby, and one elevator located at the NW corner of the building.  

   
Special Systems :  

There are no special systems that I am aware of at this time.

   

         

 

 

 

 

 

  Katherine Jenkins
  Building Statistics
  Thesis Abstract
  Technical Assignments
  Progress Log
  Thesis Research
  Thesis Proposal
  Presentation
  Final Report
  Reflection
  Senior Thesis e-Studio
 

User Note:

Note: While great efforts have been taken to provide accurate and complete information on the pages of CPEP, please be aware that the information contained herewith is considered a work-in-progress for this thesis project. Modifications and changes related to the original building designs and construction methodologies for this senior thesis project are solely the interpretation of Katherine Jenkins. Changes and discrepancies in no way imply that the original design contained errors or was flawed. Differing assumptions, code references, requirements, and methodologies have been incorporated into this thesis project; therefore, investigation results may vary from the original design.
 
Senior Thesis | The Pennsylvania State University | Architectural Engineering | AE Lab | |
This Page was last updated on December 4, 2006 , By Katherine Jenkins and is hosted by the AE Department ©2005