Thesis Progress Log
Kristen Shehab
Mechanical
Faculty Consultant – Not Assigned
Topic |
Proposed Date |
Completed |
Comments |
Find definite
size of electric load |
1.10.05 – 1.24.05 |
1.24.05 |
|
Size absorption
chillers |
|
|
|
Find amount of
steam needed |
|
|
|
1.31.05 |
1.30.05 |
|
|
Size turbine
generator. |
1.25.05 – 2.14.05 |
2.14.05 |
|
Size cooling
tower |
|
|
|
Find amount of
excess heat production from turbine generator. |
|
|
|
Find good balance
between heat and electrical load |
|
|
|
Find dimensions
of absorption chillers |
2.15.05 – 2.28.05 |
2.28.05 |
|
Place new
equipment in designated areas |
|
|
|
Find cost of new
system |
3.1.05 – 3.14.05 |
3.14.05 |
|
Compare cost of
old and new to see savings |
|
|
|
Justify amount of
money which could be put toward |
|
|
|
Finish up all
loose ends |
3.15.05 – 4.12.05 |
4.12.05 |
|
Complete thesis |
4.05.05 |
4.05.05 |
|
Create
presentation |
4.12.05 |
4.12.05 |
|