Technical Assignments

Technical Assignment # 1 pdf

Technical Assignment # 2 pdf

Technical Assignment # 3 pdf

 

 

Technical Assignment #1

       The first technical assignment focuses on the construction site’s existing conditions.  The assignment covers the delivery system for the project, a summary schedule, a summary of the systems being installed in the building, an overall cost and the relative costs per square foot.  The assignment continues on to explore the project site plan, the local conditions for construction and summary of the local market, and some more detailed information concerning the client and their particular needs.

 

Existing Construction Conditions         Monday October 4, 2004

·              Executive Summary pdf

·              Project Delivery System pdf

·              Project Schedule Summary pdf

·              Building Systems Summary pdf

·              Project Cost Evaluation pdf

·              Site Plan pdf

·              Local Conditions pdf

·              Client Information pdf

 

Summary Memo          10/4/04

The following report is a summary of the overall project.  The summary includes the way the project is being delivered and the structure of the project relationships.  There is an overview schedule with a narrative to give a rough idea of the order of activities.  The report also includes two preliminary estimates using basic estimating methods to compare with the actual contract cost.  The report includes a site plan of the existing site conditions and some temporary facilities.  There is a review of the local construction methods and conditions.  Last, but most important, there is an overview of the owner’s information and key values while building the project.

 

Executive Summary

        The Smithsonian Institution Patent Office Building is a very unique project.  Located in downtown DC, it takes up two square city blocks.  The project was delivered as a traditional Design-Bid-Build project with a CM agency to help oversee construction.  The method seemed very appropriate based on the owner’s experience and the unique demands of the project. 

            The schedule depicts the long design time as well as the congestion the project will feel due to overlap of trades when construction gets into full swing.  The site is very tight, being in the center of the city.  Also, the courtyard poses several issues due to the lack of access through the building.  The building has a wide variety of building systems, highlighted by its existing structurally arched masonry and the use of the chimneys as mechanical chases. 

            The estimates used to find cost information on the project appeared to be very inaccurate due to the unique constraints of the project.  The actual cost per square foot was much higher than the estimates bore out.  The local construction conditions in DC favor concrete construction, which will be used in the courtyard.  Also, though the project does little recycling, many of the historical materials in the building will be restored and reused.  Though the storage of the materials will lead to further congestion.

            Smithsonian Institution is a unique client who has many attributes of a government agency, however they tend to favor higher end work and finishes.  The historical nature of the building is of utmost importance to the owner, creating some unique situations and opportunities.  The key interests of the owner lay in timely completion due to the significance of the opening date, the 170th birthday of the building and the 4th of July.  Also, the level of quality expected is very high.  All in all, the project is very complex and unique.

 

Project Delivery System

        The project is being delivered using a Traditional Design-Bid-Build method with a CM agent.  The owner, Smithsonian Institution (SI), is experienced in construction.  They have three separate museums being housed within the Patent Office Building and each has very specific requirements for the space they will occupy.  SI has spent a great deal of time in design tailoring the design to accommodate each museum.  The traditional method is advantageous when the owner is experienced and has very set ideas about the design of the building.  Also, time was not a critical issue when the project began, having several years to develop the design and revise it before sending it out for bid.  SI also chose to use a CM agent to assist in the construction process.  The CM agent assists in the preconstruction phases to bring out constructability issues.  With the considerable size and high quality finishes required SI was glad to have someone else helping to monitor the project, looking for problems and other areas of concern.

 

Organizational Chart

 

 

Project Schedule Summary

        Narrative

        It is pretty obvious, when looking at the CPM schedule below, the project had a very long design period.  The design period includes the schematic design, design development, and the creation of the construction documents.  When the documents were completed there was a separate contract to perform the original demolition work as well as cleaning and repointing the façade of the building.  There was also a new roof, and new windows put on the building.  Once the first contract was finished, the bid documents for the current project went out, and the project was bid over a three year period. 

            Once the contract was awarded to Hensel Phelps to renovate the building, the first steps were the mobilization, then demolition and abatement of the building.  Due to the sheer size of the building, there is excessive overlap of activities.  Once areas have been abated of all hazardous materials the work on the chases can begin.  First structural supports are put in where necessary to support upper floors while cutting the chase openings.  Next the structural reinforcements are installed in the chases to make up for the structural brick that was removed.  Then the mechanical and plumbing systems run their risers through the chases.  Once all of the mechanical work is in place the chases can be framed.  Occurring concurrently is the demolition of the floor slabs to run the electrical conduit within the floors.  Once the conduit is roughed in the floor can be poured using concrete. 

Once all of the basic MEP work is roughed in the chases can be closed, followed closely by drywall and plaster.  When all of the necessary coats of plaster are in place the painter can come through and paint the walls and ceilings.  When the painter is through with certain space, the area can be fitted with lights, louvers, fixtures, etc.  The flooring is then installed, whether it is marble, tile, carpet, or wood.  Once the MEP fitout is well under way, the commissioning of the various systems can begin.  When an area has all of its finishes, the museums can begin to move in and take them over.  Lastly, there is some sitework that needs to be accomplished as well as the demobilization of all of the trailers, equipment, etc. 

 

 

Building Systems Summary

Demolition

·        Abatement - There is abatement requirements for both asbestos and lead.  The lead is existent in the current paint on the walls.  The paint has not been removed ever since the original construction of the building, and has undergone several renovations and remodeling efforts.  There was limited asbestos since the building was complete before asbestos was popular and therefore was only used in a limited capacity during the last major renovation in the 1950’s. 

·        Demolition – The major area of demolition for the project relates to the expansion of the existing chimneys to make room for the pipe chases.  Throughout the project there are over 500 chases that need to be located and opened, typically from floor to ceiling.  Then they need to be expanded, often both wider and deeper, to accommodate the duct or pipe running vertically through the space.  There is also some demolition required for through wall penetrations for the duct and pipe as well.  Also, there are an extensive number of through floor penetrations for electrical conduit since it is run in the floor in all of the gallery spaces.

 

Structural Steel Frame

·        There is steel reinforcement, steel angles, needed for the existing granite slab throughout the North and West wings of the third, third mezzanine, and fourth floors. 

·        In the mechanical chases, often steel C channel is bolted into the masonry walls for support if the chase is expanded from its original size.

·        In the courtyard there is structural steel spanning the auditorium area.  The connections are mostly bolted, though at the beam splices there are full penetration welds as well.

·        The erection of the steel requires a 500 ton mobile crane with an extension to reach over the building into the courtyard.  The locations to set up the crane were limited due to the downtown location.  G Street between 7th and 8th Streets needed to be closed for two weeks to erect the steel in the courtyard.

 

Cast in Place Concrete

·        The formwork for the concrete for the vertical placements was all built in place from wood, or used the soldier beams and lagging that were in place for the excavation.

·        The formwork for the piers and pile caps consisted of some gang forms and wood forms for some of the unique shapes required.

 

Mechanical System

·        The mechanical system is split into two separate parts, one running up from the basement through the second floor, the other starting at the top floor and feeding down to the third floor.

·        The mechanical rooms for the lower floors is are located in the basement of the West wing.  The mechanical and electrical equipment take up almost the entire basement of the West wing.

·        The mechanical rooms for the upper floors are in the North wing and the north half of the West wing. 

·        The mechanical system is an all air system with vertical distribution using duct through existing chimneys.

·        The fire suppression system is an all water system.  Due to the historical nature of the building there are some spaces that do not have sprinklers so as not to take away from the historical nature of the space, such as the Lincoln Ballroom.

 

Electrical System

·        The electrical system feeds the building with two 13.8 KVA lines coming into the basement at two separate points.

·        The building, besides having two separate feeds, has an UPS system with a diesel generator to maintain power.

Workers moving transformer into basement

 

Masonry

·        The building is an existing load bearing masonry building.  Near the foundation the walls are several feet thick. 

·        The majority of the building is brick; however there are granite and marble columns, and the façade is made up of sandstone, granite, and marble.

·        Where there has been demolition the building is, as much as possible, to be built back with brick and block.  The use of similar materials lowers the risk of structural issues related to uneven expansion and contraction.

·        A unique note for the masonry is when new brick is put into place; the brick used must be uniquely different from the existing brick.  The specifications require the unique brick to ensure that in the future it is easier to identify which was original and which was installed in the renovation for historical purposes.  The contractor therefore used both blonde and concrete bricks for the new construction.

·        Scaffolding was required in the interior of the building when doing work on the chases.  The scaffolding was used for two reasons: 

·        To support the existing structure when demolition undermined supports for the floor above

·        When doing work at some of the higher elevations.  Some of the grand spaces have ceiling heights approximately 40 feet above the existing floor.

 

Support of Excavation

·        The support system for the excavation of the courtyard consists of soldier beams and lagging.

·        The support system remained in place and served as the rear form for the cast in place concrete walls in the courtyard.

·        Since the excavation had portions of existing building along the west, north, and east faces dewatering was only an issue due to rain.  When necessary a pump was brought in to dewater the courtyard.

 

Project Cost Evaluation

Actual Cost

·        Total Building Renovation Cost per Square Foot (per base bid):  $261.78/SF

·        MEP System Cost per Square Foot (Mechanical, Electrical, Plumbing, Fire Protection):  $94.24/SF

 

D4 Cost Estimate

·        What is D4? - D4 is software for estimating projects based on historical project costs.  The program has a database of projects and the database can be searched by a list of criteria to find projects similar to the project being estimated.  Once a list of similar projects is put together, the user chooses the projects best most like their project and using the software can “Smart Average” them.  The software weighs the different buildings to account for number of floors, floor heights, etc.  The outcome is an estimate split up into the 16 CSI divisions.  The user then has a base estimate to work from and can make adjustments for the unique characteristics of their actual project.

·        D4 Base Estimate

·        Adjusted Estimate

 

CSI

Division

Area

D4 Original Estimate

Adjustment

New Amount

Reason for Adjustment

1

General Requirements

$5,298,710

$6,000,000

$11,298,710

4 trailers, Staff of 20+, 3 year job,

trucks for supts, money for parking

2

Sitework

$5,496,093

$5,000,000

$10,496,093

extensive lead & asbestos abatement,

demolition work, CY work

3

Concrete

$10,924,196

$0

$10,924,196

repouring all of the floors,

CY foundations & floor

4

Masonry

$2,109,917

$1,000,000

$3,109,917

all masonry bldg, lots of repair work

5

Metals

$4,910,729

$0

$4,910,729

 

6

Woods & Plastics

$1,030,431

$2,000,000

$3,030,431

repairing historical wood, large amount

 of exposed wood

7

Thermal & Moisture Protection

$1,754,023

 $0

$1,754,023

 

8

Doors & Windows

$1,942,231

$0

$1,942,231

 

9

Finishes

$4,763,065

$3,000,000

$7,763,065

high end finishes, hand made,

materials from overseas

10

Specialties

$3,573,145

$0

$3,573,145

 

11

Equipment

$1,776,191

$0

$1,776,191

 

12

Furnishings

$1,348,894

$1,000,000

$2,348,894

casework, auditorium seating

13

Special Construction

$1,136,200

$2,000,000

$3,136,200

blast resistance, measurement &

control instrumentation

14

Conveying Systems

$1,847,123

$2,000,000

$3,847,123

installing multiple elevators

15

Mechanical

$7,791,697

$10,000,000

$17,791,697

two systems, extensive ductwork,

new sprinkler system

16

Electrical

$6,723,695

$10,000,000

$16,723,695

high end security system,

new data lines, UPS system

 

Totals

$62,426,340

$42,000,000

$104,426,340

 

 

RS Means SF Cost Estimate

Dimensions:  Courtyard  -  the new construction portion of the building.

Assumptions:

·        1 Story Building

·        24’ Story Height

·        Precast Concrete w/ Steel Frame

Revisions to Standard Data:

·        Interpolation between 24,000 SF and 27000 SF to get numbers

{Formula = 24,000 + (25,000-24,000)/(27,000-24,000)}

·        Modification from 640 LF of Perimeter to 700 LF of perimeter (4.70 / 100LF)

$2.82/SF  =  (60 LF * 4.70 / 100)

·        Change to Padded Seats costs $207 EA for 300 seats

$207 * 300 = $62,100

RS Means Estimate:

 


$111.81 / SF

+ $2.82 / SF

 

 

 

 

 

$114.63 / SF

X 25,000 SF   =

$2,865,750   +

$62,100  =

$2,927,850

 

 

 

Comparison of Estimates to Actual Costs

·        D4: 

The D4 Estimate was considerably lower than expected.  The projects used to “Smart-Average” in order to come up with an estimated project cost were not very similar to the Smithsonian Institution Patent Office Building.  The projects used ranged from an arts center, to the National Archive II bldg.  The trouble lies in the unique nature of the Patent Office Building.  Estimating for a renovation project varies significantly from building to building because of each building’s distinctive history.

 

·        RS Means: 

The RS Means estimate appears to below what the courtyard should probably cost.  The Smithsonian Institution is sparing no expense for their project, and the high end finishes they are using is not apparent in the SF cost of the courtyard.  The SF cost is less than half of what the SF cost for the entire building is for the base contract.  Since the courtyard is basically a new project within the renovation, the cost per SF should probably be a little less than the rest of the building, since there is limited demolition and no abatement.  The estimate also cannot show the lack of access to the courtyard that will raise costs of doing any work requiring equipment in the area.

 

 

 

Site Plan of Existing Conditions

·       Site Plan featuring temporary facilities, property and boundary lines, existing and new utility lines, traffic flow, and adjacent buildings.  (Site plan is not currently complete but will be soon)

 

Local Conditions

        Preferred Methods of Construction

·        Washington, DC is well known for its concrete construction due to the height limitations on buildings within the city and the ability to have smaller space between floors with a cast in place concrete building rather than a steel structure. 

·        Since the site is downtown, there is limited space within the construction boundaries.  Nonessential uses of space are, when possible, moved off-site.  For example, parking is off-site at local parking decks and other available locations.

Recycling/Dumping

·        Recycling is being done for the office paper used on site.

·        There are several materials in the building that are being restored and reused.  There are existing tile and marble floors that have been taken up to be cleaned and put back in place. 

·        Tipping fees in the Washington area run $350 to get a 30 yd dumpster pulled and dumped.

Soil/Subsurface Water Conditions

·        The soil found when excavating in the courtyard …

·        Since the courtyard is within the building footprint, there were minimal problems with onsite water.  The only time it was an issue was due to inclement weather.

 

Client Information

            Smithsonian Institution

·        “The Smithsonian, as an independent trust instrumentality of the United States, conducts scientific and scholarly research, administers the national collections and performs educational public service functions, supported by its trust endowments and revenues, gifts, grants, contracts and funds appropriated by the Congress.”  (Taken directly from http://newsdesk.si.edu/)

·        The Patent Office Building is going to house three distinct art museums:  The National Portrait Gallery, The Smithsonian American Art Museum, and The American Art Archives.  The building is being renovated because of a number of issues related to the age of the building.  When a building reaches a certain age the mechanical, electrical and plumbing systems become outdated.  There is significant wasted energy, and there are a number of hazards related to the asbestos and lead in the building.

·        The total cost of the building, including previous work to clean the façade, fix the roof, and replace the windows, combined with design and development costs and some planned future work, will be approximately $210 Million.

·        The quality expected in the building is extremely high.  The level of finishes required in the interior spaces are the highest possible on their respective scales.  Many items are hand made, or made to resemble the buildings original makeup, as well as restoration of existing materials that have undergone 170 years of wear.  The evidence of the strong interest is very clear in the specifications for the building through the quality control measures and the very specific nature of the specifications for finish materials.  Also, the project is an historical building as well as an art museum, both of which are of an extremely public, visible nature and the visitors coming into the building will have high expectations, therefore the owners want to meet the expectations coming in.  Also, there is a whole section of the specification related to the historic nature of the building.

·        The schedule is designed to have the building substantially complete and open to visitors on July 4th of 2006, 170 years after its original construction on a significant American holiday.  The schedule includes some phased occupancy to allow the museums to all have some space within the building before the grand opening, as well as working out the commissioning of the systems and the move-in of the significant amount of art to be displayed.

·        The safety is of utmost importance due to the hazardous contents and the age of the building creating the potential for very dangerous situations.  The owners’ emphasis on safety can be clearly seen through their hiring of a general contractor with a track record for safety, and their requirement of a full-time safety manager on site throughout the entire project.

·        There is, as mentioned above, phased occupancy for the building.  The entire West wing of the building is turned over to the owner more than a year in advance of the substantial completion of the project. 

·        The keys to completing the project to the owner’s satisfaction lay in:

·        Completing the project in a timely manner, due to the significance of the grand opening date.

·        Providing a project up to the quality expectations of the representatives of the multiple museums who will be occupying the space.

·        Completing the project within a reasonable range of the budget.

·        Having no major injury throughout the construction.

 

Technical Assignment #2

            The second technical assignment concentrates more on some of the key features of the construction.  There is a more detailed schedule, shifting from 30 to 200 items.  There is an assemblies estimate of a particular portion of the building.  There is a summary and analysis of the contracts employed on the project.  The assignment asks for a breakdown of the way the project staff is allocated.  The assignment also includes the process of coordination that was followed as well as the areas where issues occurred.  The last item is a summary of the meetings attended at the PACE Roundtable Seminar. 

 

Analysis of Key Construction Features              Wednesday October 27, 2004

·       Executive Summary  pdf

·       Detailed Project Schedule  pdf

·       Assemblies Estimate  pdf

·       Contracts  pdf

·       Staffing Plan  pdf

·       Design Coordination  pdf

·       Critical Industry Issues  pdf

·       Soil Conditions  pdf

 

Summary Memo          10/27/04

The following report is a a more in depth analysis of certain features of the construction that set this project apart.  The analysis covers a more detailed project schedule broken down by wing and by activity.  There is an assemblies estimate of the structural system in the courtyard.  There is an overview of the contractual relationships on the projects and their appropriateness.  There is a staffing plan for the general contractor showing the way the project is broken up and managed.  The design coordination section covers the plan for coordinating the installation of the MEP systems in the building and some of the areas of conflict.  Included is a write up of certain sessions from the PACE roundtable meeting held at the Penn Stater Hotel & Conference Center on October 7th.  Last is a brief overview of the soils report that was not available for the first technical assignment. 

 

Executive Summary

Included in this submission are a detailed project schedule, an assemblies estimate  of the buildings courtyard structural systems, an overview and evaluation of the contracts used on the project, the staffing plan for the general contractor, an overview of the plan for the MEP coordination, a write-up of the PACE roundtable event and an overview of the existing soils conditions on site.  The highlights of the submission are the dual systems employed in the courtyard structural system and the differing costs.  The contracts employed on the project are rather straight forward with lump sum contracts being used in all instances.  The highlight of the contracts was the use of a best value selection process for the general contractor.  The staffing plan is of a typical nature for how Hensel Phelps usually staffs a job, though due to the size of the job there is a large staff on site.  The age and historic nature of the building introduce a number of interesting aspects into the design coordination for the MEP systems.  The key area of trouble in the field tends to come from the conversion of the old chimneys into mechanical chases.  The critical industry issues write up covers the Performance Contracting, Green and High Performance Buildings, and the Leadership Jump Start sessions.  The direction the roundtable has pushed my research interests has been towards LEED rating and green building systems. 

 

Detailed Project Schedule

 

 

 

 

 

 

 

 

Assemblies Estimate

The assemblies estimate looks at the structural systems in the Courtyard of the Patent Office building.  The courtyard’s structural elements were chosen because the courtyard has two different structural systems being used.  The west half of the courtyard is structural steel with a one way slab.  The east half is a structural two way slab with concrete cast in place columns.  Around the perimeter of the courtyard is a structural concrete wall with varying height (the auditorium section in the west half slopes downward and has higher floor to ceiling height.  The courtyard will also be looked at in detail in the third technical assignment with a detailed estimate.

 

Material Takeoff

Material Takeoff Data

 
 Data

Item

Dimension

Quantity

CIP Columns

14' Tall, 15" square

35

Steel Columns

18' Tall, 48 plf

24

Steel Columns

18' Tall, 58 plf

5

One Way Slab

30' x 6'

1

 

200' x 7'

1

 

20' x 40'

1

 

53' x 16

1

Totall

 

3250 SF

Two Way Slab

80' x 43'

1

 

53' x 3'

1

 

33' x 6'

1

Totall

 

3800 SF

Slab on Grade

 

7050 SF

W shape Beams & Girders

3250 SF

1

CIP Walls

18' x 53'

2

 

18' x 16'

1

 

14' x 75'

2

 

14' x 53'

1

Total

 

5000 SF

 

RS Means Costwork Estimate

Source

Line Number

Description

Quantity

Unit

Ext. Material Incl O&P

Ext. Installation Incl O&P

Ext. Total Incl O&P

Zip Code Prefix

Type

Release

Assembly

A10301202280*

Slab on grade, 4" thick, light industrial, reinforced

7,050.00

S.F.

$13,481.43

$16,020.35

$29,501.78

20004

Union

2003

Assembly

B10102030900*

CIP col, sq tied,200 K,14' sty ht,14" col,196 PLF wt,4000 PSI conc

35.00

V.L.F.

$407.73

$1,679.63

$2,087.36

20004

Union

2003

Assembly

B10102083800*

Steel columns,125 KIPS,20' unsupported height,48 PLF weight,8" wf

24.00

V.L.F.

$851.76

$149.93

$1,001.69

20004

Union

2003

Assembly

B10102085000*

Steel col,200 KIPS,20' unsupported height,58 PLF weight,12" wf

5.00

V.L.F.

$215.08

$31.23

$246.31

20004

Union

2003

Assembly

B10102173800*

CIP slbs, 1 way,sgl 15' span,200 PSF supimp,8.5" thk,306 PSF tot

3,250.00

S.F.

$13,394.06

$23,719.41

$37,113.47

20004

Union

2003

Assembly

B10102206600*

CIP bm&slb,2 way,25x30',200PSF supimp,20"col min,8.5" slb,341PSF tot

3,800.00

S.F.

$22,801.90

$40,275.82

$63,077.72

20004

Union

2003

Assembly

B10102418980*

Wf b&g,35x30' (BXg),200 PSF supimp,36" d,.874 SF/SF fprf,281 PSF tot

3,250.00

S.F.

$39,502.13

$16,420.98

$55,923.11

20004

Union

2003

Assembly

B20101017400*

Conc wall reinforced, 8' high, 12" thick, plain finish, 3000 PSI

5,000.00

S.F.

$25,254.00

$71,765.85

$97,019.85

20004

Union

2003

 

 

 

 

 

$115,908.09

$170,063.20

$285,971.29

 

 

 

*Note:  The table above was put together using RS Means Costwork 2004 Program which allows the inupt of the zip code of the project for location cost calculations as well as the year of the project start to convert for time value of money. 

 

When reviewing the data it is interesting to not the steel system employed on the west half and the concrete system on the east half show a significant difference in price.  The column systems are comparable, but when looking at the slabs employed on both, the one way slab used on the west half cost about half again as mush as the two way slab on the east half when the cost of the steel beams and girders are taken into account.  There seems to be a prime opportunity here to find an alternative system that would make the courtyard one consistent structural system (making construction simpler) and at the same time making the system itself less expensive from a materials standpoint.

 

Contracts

Hensel Phelps - GC

·        The main contract for the construction of the building was a lump sum contract given to the GC on a best value decision process

·        Hensel Phelps bid was, in fact, the highest of the bids put in

·        The reasoning behind the Best Value selection was mainly due to the historic nature of the project and the emphasis on preservation of the building and its unique materials

·        The owner felt that using a lowest bidder selection process would result in a lower quality final product from the desired results

·        The project has no OCIP or CCIP requirements, there are insurance requirements, but they are of a standard nature for construction projects and in line with Hensel Phelp’s normal insurance requirements, (eg. General Liability, Workers Compensation, etc.)

·        The bonding on the project is a little unusual, the GC has a performance bond for 100% of the contract value, however the payment bond is only for 50% of the value of the base contract

·        The contract contains no incentives, rewards, shared savings clauses, nor liquidated damages clause

 

 Subcontractors

·        The contracts between Hensel Phelps and its subcontractors is a standard lump sum contract used for all of its subs

·        The insurance and bonding requirements from the owner are passed on in the same format to all of the subcontractors

·        The contracts follow the same lump sum format as the main contract between Hensel Phelps and Smithsonian for simplicity of management, changing to a different style of contract could lead to a variety of complications

 

 Hartman-Cox Associates

·        The contract with the architect was originally on an hourly basis, with the architect submitting a log of the hours spent by themselves as well as the consulting engineering firms

·        The contract was amended later to change to a lump sum contract due to the excessive tracking work needed by both the architect and the owner in order to maintain proper billing procedures

 

 Bovis Lend-Lease

·        The contract with the Construction Management Agency is assumed to be a Lump Sum contract, which would fall in line with the rest of the contract types

·        The CM is focused on managing the construction process so the insurance requirements would match those of the contractors and subcontractors, with the exception of liability relating to the work in place

·        It is possible that the CM may have Errors and Omissions Insurance due to their  involvement in constructability reviews and the potential for liability in that area

 

Appropriateness of Contracts

Hensel Phelps

·        The lump sum contract, chosen with the Best Value selection method, seems quite appropriate due to the focus of the owner’s interests on the quality of the final   product

·        Using the Best Value process allows the owner to weight other aspects of the bidding organizations including the experience of the project team and the thoroughness of the construction plan, budget, schedule, etc.

·        Smithsonian Institution has worked with Hensel Phelps on other projects in the past, namely the new National Air and Space Museum at Dulles Airport, which may have influenced Smithsonian’s decision to use Hensel Phelps

 

 Subcontractors

·        Due to the size of the project and the complexity, the use of a boilerplate contract simplifies the process to simple modifications from a universal base contract

·        There are obviously some modifications based on scope of work and preferences of subcontractors on certain terms and clauses, however the contracts are very consistent

·        Using a boilerplate contract for all of the subcontractors seems very appropriate  considering the number of subs employed on the project and the long duration

·        The contract type also is appropriate because of its alignment with the main contract between Smithsonian and Hensel Phelps

 

 Hartmann-Cox Associates

·        The use of an hourly contract for the design firms seemed very inappropriate

·        The fact that the contract did not match the project was born out when the contract changed to a lump sum partway through

·        The use of the lump sum seems appropriate, again, because of its alignment with the contracts for the rest of the project and the amount of work it saves for both the designer and the owner

 

 Bovis Lend-Lease

·        Using a lump sum contract is the right choice for the construction management firm for much the same reason as for the general contractor, the level of quality requires a knowledgeable and experienced builder

 

 The alignment of all of the contract types saves the owner a considerable amount of work because the system they use to track all of the companies in their employ is all the same format and they are getting billed in the same manner by all parties.  The owner is experienced in construction and was pretty wise in their decision for the proper delivery method for the project and the selection process they used in choosing a contractor.

 

Staffing Plan

 

 

 

Staffing Plan

·        The staffing plan for Hensel Phelps is fairly standard following the set up they typically use on a project

·        The main division is between the field staff and the office staff

·        The Project Manager heads the office team

·        The Project Manager is in charge of all of the project documentation and overseeing of the contractual relationships on the job

·        The Project Engineer is directly under the project manager

·        The Project Engineer performs the accounting and key documentation for the project

·        The Project Engineer also serves as the main conduit of information flow between the owner, architect, Construction Manager, and the Office Engineers

·        The Office Engineers function under the Project Engineer and are divided up among specification sections and their respective subcontractors

·        The Office Engineers are responsible for the submittals, RFI’s and necessary procedures related to their spec sections and the respective documentation

·        There is also an Office Engineer assigned to tracking the change orders and potential change orders due to the vast number of changes on a project of this size

·        The Project Superintendent is the respective head of the team that runs and performs the  actual construction of the building

·        The Project Super focuses on getting the project built and maintaining the quality, schedule, and safety aspects of the job

·        The Project Super also runs the construction of the mock-up to work with subcontractors performing their work for the first time and to ensure the result meets the expectations of the designers and the owner

·        Directly under the Project Superintendent are several Area Superintendents and General Foreman who are responsible for specific sections or aspects of the building

·        The Area Supers are divided up with one taking the sitework and courtyard construction, one taking the lower half of the existing building, and one taking the upper half of the building

·        The General Foreman are split into the Masonry Foreman due to the extensive masonry work throughout the building, and a Foreman in charge of the chases/vertical risers for the mechanical work

·        The Area Supers and the General Foremen are all designated certain managerial aspects for the project, such as equipment management, material storage, etc.

·        Under the Area superintendents are the Field Engineers

·        The Field Engineers are responsible for the layout of work for the respective areas of the Supers

·        The connection between the field and the office teams lies in the Quality Control department with a manager in the office to focus on documentation and a field inspector to review work and ensure proper installation

 

Overall

            The staffing set up for the project works well.  Hensel Phelps is a large firm and has been using the same general staffing plan for a number of projects over many years.  The main complication for this project lies in the size of the project and the coordination of the large staff it requires.  There are communication problems, though daily meetings between the field staff and the office staff clear up most difficulties and help focus the work for that day.  The project is manned at approximately the right number of personnel.  Most staff members work approximately a 50 hour week.  Adding one or two people to the project would lighten the individual load of a few people, but would add to the coordination needed for the whole project and in the end most of the staff’s load would not change significantly.  The integration between the field and the office is fairly strong.  Hensel Phelps has a fairly regimented program for personnel coming up through the ranks and upper level personnel are familiar with the duties of the other staff and know who’s responsible for which tasks.  They are also there to assist in making sure the newer staff can do the work expected of them.  There is a strong atmosphere of guidance without overbearing control.  The staffing plan is also distributed to the subcontractors, Construction Manager, the Design team, and the owner.  Sharing the staffing plan with the project team allows for the communication to go more smoothly between the different entities on site.  The owner and all of the subcontractors still have a main point of contact, but they are also aware of the duties of the entire team and it is easier for them to know whom to consult in various situations and

conflicts.

 

 

Design Coordination

Scope / Contract Requirements

            Coordination of MEP work is required by contract for the Mechanical/Plumbing,

Electrical, and Fire Protection Contractors.  The contracts call for the overlaying of respective shop drawings to identify areas of conflict and the resolution of those conflicts.  The first step required is for a schedule of the order of coordination drawings listing the areas of main

concern and the dates when the coordinated drawings will be submitted to the designers.  The mechanical contractor, Pierce Associates, will take the lead in coordinating the drawings.  

 

 Intensity

            Since the building is an art museum, the mechanical coordination does not appear at first glance to be an intensive one.  The age of the building and the unique structure make the building rare by nature, the systems used in it have to function accordingly and therefore tend to be somewhat complex so they do not impact the nature or use of the building.  The mechanical areas will require a fair amount of coordination due to the amount of equipment needed to supply a building with such immense size. 

            The use of an all air system increases the amount of space the mechanical system will take up.  Duct work is one of the most space consuming systems in a building.  The building’s layout by wing causes the systems to have long runs of duct, pipe, and conduit in order to feed the various spaces in the building.  On top of the layout, the system is split into two parts, one feeding up from the basement and the other feeding down from the fourth floor.  Having two mechanical rooms means having to coordinate two separate mechanical rooms. 

            One of the details of the building that simplifies the coordination process is the lack of ceilings in the various spaces.  There are very few spaces in the building that have a ceiling besides the structure of the floor above.  The mechanical rooms and the basement spaces have exposed MEP work running openly.  The electrical conduit is run in the floor slabs.  Most of the duct that feeds the spaces is run in vertical chases that do not have horizontal runs on the floor but feed the space from the sides.

            One of the unique areas that requires coordination is the cooling tower.  The cooling tower requires a new steel structure to be erected on top of the roof.  The cooling tower will require coordination between the steel and the mechanical lines that feed the cooling tower.

 

 Deadlines

            The shop drawings, after the plans have been coordinated, must be submitted to the respective engineers for approval of any changes that needed to be made.  The schedule of submissions for the drawings was drawn up in advance based on the construction schedule of when those areas would be built. 

 

Problems, C/O’s & Field Conflicts

            The key problems associated with the MEP systems focus on the use of the former chimneys as the riser space for the mechanical chases.  The chases are typically 1 ft by 1 ft when they are first opened up.  The chases need to hold the ductwork, as well as some other plumbing and mechanical risers.  In almost every case the chases need to be widened in order to fit the MEP work in place.  Widening the chases creates a number of structural issues due to the age of the building and the fact it’s structural masonry.  There are questions about the structural stability of all of the extra holes and openings being made.  Also, the reinforcement to support the structure is typically steel channel which expands and contracts differently from masonry and could lead to cracking and other structural issues.

            The age of the building also means that there are not a good set of As-Built drawings to work from when the systems were designed.  Many problems arise when opening the chimneys to see the existing size.  Often the structural engineer has to come to site because a chases do not conform to the typical structural details for reinforcing shown in the drawings.

            Once installation of the MEP rough in and equipment began, weekly coordination meetings started.  The meetings look at the 4-week look ahead schedule to find areas the subcontractors will be working that may have conflicts.  The conflicts are worked out in advance to minimize schedule impacts

            One of the solutions for coordination in the West Basement, the main mechanical and electrical space, was the use of metal racks to support some of the MEP runs.  The racks hold up the lowest layer of ductwork and piping.  The system enables the contractors to have two tiers of MEP systems running down the corridor in the basement.  The system also detracts from the amount of structural support needed from the arched masonry ceiling above. 

            One of the major changes that occurred with relation to MEP coordination was in the East Basement.  Originally the MEP systems were to run exposed from the ceiling as in the West Basement.  The space is going to be used for certain offices and the occupants did not want exposed systems running through the corridor (the ceiling height was low to start).  The systems were changed so the mechanical and  electrical systems run in the slab, requiring the excavation of trenches due to the amount of conduit and ductwork going down the corridor.  The change required an extensive amount of coordination to locate where the crossover of systems was underground and also to work around the foundation as much as possible rather than coring through the footings. 

In the area where there is a ceiling (North West of the 3rd floor) there is a conflict of the mechanical equipment due to limited space above the ceiling, resulting in the lowering of the ceiling.  In the Luce Center, one of the “Great Spaces,” there are display cases which require electric hook ups, the conduit needs to be run under the floor for appearances sake and the floor is existing slate and not easily fixed in case of a mistake or change.

            In the courtyard the MEP systems have been re-coordinated several times because of multiple changes from the owner, there are extensive Mechanical and Electrical systems running above the ceiling in order to support the auditorium.  The re-coordination effort is a strain on the personnel because they have already performed the work and are in the process of planning the construction only to have the whole area changed and they have to start again,

almost from scratch.

 

Critical Industry Issues

Session 1:  Performance Contracting I:  Rewards & Incentives

            During the first session, it was interesting to learn the contractors’ views on the idea of rewards and incentives in contracts.  All of the contractors tended to be agree that some sort of reward or incentive was usually a good thing in a contract.  There was unanimous approval for shared savings clauses. 

            There was general agreement that performance based fees worked, though they felt there should be some more objective criteria for assessing the performance.  They referred to the more subjective areas as “working for tips.”  The other issue raised about performance based fees was the potential for personality clashes between the contractor and the owner that could lead to unfair assessments for the contractor. 

            When the idea of incentives came up there developed some interesting conversation about the manner in which owners went about dispensing the incentive.  One example where an employer wanted to hand checks directly to the GC’s employees was considered a serious issue.  The manager felt the payment could lead to a “mutiny” from other employees on other jobs who were not being compensated in an equivalent manner when they were working to the same level.  Also, the potential for new employees could come to expect the incentives as money they were entitled to on every job.  Also, because the employees were new they might not perform in the owner’s best interests but try to get the most money out of the owner, in effect working in their own best interest.

            Other incentives that were discussed were early completion incentives, safety awards and the potential for more work from the owner.  One of the questions raised during the discussion was whether or not early completion bonuses led to an overall lower cost for the project for the owner due to the shorter period on site, or if the contractors were building in extra money into their bid to cover the cost of earlier completion. 

            After the discussion of fees the discussion moved to try to define what high performance contracting actually meant.  The industry members present tended to agree that it went beyond being on time and on budget for the project.  They felt serving the customer’s needs, beyond the requirements of the contract, was where the step above came from. 

            The key to being a high performance contractor, from the point of view of the companies present, was in the people working for the company.  The personnel needed to be able to adapt to changing conditions, have continuity in education, and that success for the project needed to be defined up front.  When the project was of significant length, the success might need to be redefined multiple times.  The question was raised by the students about the relationship between contract incentives and repeat clientele.  The industry members said that most of their work where they had incentives was with customers who were repeat clients.

            The last topic discussed was the idea of a performance specification.  The industry members said that if the spec was a “true” performance specification then it would work, however most performance specs were “hybrid” specs where some items were specified by name and took away the performance potential for some of the systems.  Also, there tended to be problems where there were too many customers to please, such as at the Pentagon, where so many people had a preconceived notion of what they were getting.  Also, the key seemed to lie in the submittal process to ensure the products submitted met the intent of the specification, and the owner needed to be involved to see exactly what they were getting. 

            Another question raised by industry members was why do incentives not always work in  contracts, certain contractors seem to not work toward getting the incentives.

 

Session 2:  Emerging Markets II:  Green and High Performance Buildings

            In the second session the topic started with why do people pursue green buildings.  The main responses seemed to be driven by the bottom line, whether that was governmental incentives, higher turnover of merchandise, improved marketing, or possible fundraising opportunities.  The questions that were raised were what are the legal aspects of a contractor pursuing the LEED certification for a building, and one of the subs drops the ball, taking the certification down a level.  Who is now the responsible party if the building does not reach the level specified?  Is it the responsibility of the GC when a sub came up short?  What are the damages to the owner? 

            The conversation then turned to a delineation of what exactly we were talking about.  The comment was raised that we were of course talking about LEED, since it’s possible to be green without getting a LEED certification.  Another comment was thrown out that LEED is basically equivalent to Energy Star on electrical appliances, etc.  If someone wants a TV that uses low energy then they buy one with an energy star symbol, if they want a building like that, they expect a LEED certificate. 

            The perspective then moved to that of the companies.  What are the actual costs of gaining points at each certificate level.  How do the costs change by region.  Also, the business case needs to be proven for companies to really be on board.  Someone brought up the point that when people built houses, etc., a long time ago they were designed to be comfortable.  When air conditioning was developed we stopped designing that way and just loaded up on the AC.  Now we’re just reverting back to what made sense in the first place. 

            The suggestion was made to come up with a checklist of reasons to obtain each point with the incremental cost changes associated with each point.  For example, if someone were looking at the point for the bike rack.  The checklist would show the value/intent of the point, a few reasons why someone might choose it, state the up front cost of buying the appropriate number of bicycle racks and showers if necessary, and the life cycle cost increase or decrease for the point.  There would need to be a significant amount of study to show the cost per SF to get each point since they are somewhat interdependent.  It might be possible to generalize it to what is the minimum cost per SF to step from the bare minimum of one certification to the next.  There would be less adjustment and the dependence of the points would balance themselves out.

            Another area that could be researched would be which points are most and which are least often obtained on a project.  Then also correlate them to what level of certification the building received.  One area of suggestion, when comparing the US to Europe, was cradle to the grave analysis of energy input into various items involved in construction, as well as LEED point items.  One question raised was how many owners get a LEED certification, then decide not to pursue the certification on another project.  What reasons do they have for this, is it the cost of documentation, or are the projects no longer green, etc. 

            When recycling moved into the forefront of the discussion, the issue was raised of how could the logistics of recycling be handled.  The area of concern seemed to lie in the enforcement of the recycling plan.  It was suggested that recycling could be improved significantly through education of the workers, in the same manner that safety has.  Also, planning to minimize waste on site can save a significant amount of non-recycled garbage. 

 

Guest Speaker:  Chris Hewitt of AISC:  “Managing steel prices and a volatile market.”

            Chris gave a brief overview of the myriad of issues that were causing the price of steel to rise.  He started by showing how originally the price of steel was actually artificially low in the US due to an oversupply, a strong dollar, and cost pricing of the milling and fabrication.  Recently, China has been beginning to build up its infrastructure, and with the size of China the affects of their purchasing has had a significant financial impact worldwide.  On top of that the American dollar value has dropped, shipping prices are rising, and global demand has increased.  All in all the price of steel has just been moved much closer to the global price of steel.  The effect of China’s influence is not limited to the steel market, the effect will also be felt in wood and cement as well. 

            He then reviewed the five V’s that have an influence on the steel prices.  Volume of work is actually less than what the American steel fabricators can handle currently.  The businesses can handle about half again as much work as they are currently performing (throughout the country, that does not mean that individual companies can handle that much more work).  Velocity, the standard mill and fabrication cycle has not changed recently by any significant amount.  Value, mill prices have risen by approximately 50%, raising project costs directly by 1.5-2%.  Variety, many contractors are stockpiling rebar in stock sizes to keep their prices artificially low for the time being.  With steel, stockpiling is not easy due to the large variety of sizes specified in drawings.  Volatility, the price of steel has been unpredictable for the last 9 months, which has led to higher prices mainly to protect those giving prices.  All of the issues together are leading to an increase of 10-12% for projects overall, regardless of the materials used. 

            Some of the ways contractors can manage the process is to bring the specialty contractors in early to get their perspective and influence in minimizing the cost to the project.  Some of the other ways to manage the costs are through the management of expectations, through realistic risk identification and acceptance, consistency completeness & coordination of structural drawings. 

 

Session 3:  Leadership Jump-Start for Entry Level/Undergraduates

            The last session of the day focused on Leadership, the characteristics needed for leaders, and the ways new hires can learn to become good leaders.  The discussion started out in simple terms, set expectations, learn to be a good follower as a starting point to being a good leader.  One of the keys was in observing traits of good leaders and people that others want to work for.  Too often students rely on their technical skills, they need to learn to delegate and give proper guidance when delegating.  Also, the delegation of responsibility and authority need to go along with the onus of the task. 

            The students felt that they could benefit from more feedback from companies.  The industry members replied that the students needed to learn to read the feedback they were already getting.  Possibly a class on reading body language would be beneficial.  The idea that motivation and initiative were the most commonly sought traits arose.  Also, the idea that the company’s goals, mission, values, vision, etc., should be thoroughly driven into the new company members.  Also, new hires should be given an understanding of the potential growth path that is available to them and that through their understanding they can define their own path through the company. 

            The value of appropriate mentors was touted as a strong method for weaving new staff into a company.  The comment that if you don’t make a mistake then you’re not trying hard enough.  The new hires should make mistakes, but also should own up to them immediately so they have an opportunity to learn and grow.  Also, the reasons for making the mistakes should be worked through so the errors are legitimate and educational, not through laziness or

ignorance.  A potential research question is what first and second year hires in a company find to be their most valuable resources and what resources they wish they had available, as well as what they wished they new about companies before they went to work for them. 

            The areas that industry members said they were expecting from new staff was commitment and flexibility, the challenge and reward aspects of the construction industry as an incentive, people have to be ready to respond and make decisions because those are what’s needed in construction.  Also, new members of the staff should be ready to challenge the company to make them work, learn to be good at face to face conversation.  The issue of

reading body language was reiterated.  Lastly, the effective use of email since the “now” generation has a tendency to avoid confrontation.

 

 

Soil Conditions

  • The soils found on site were consistent with the prevailing soils in the area, mainly Silty Sand, Clayey Sand, and Lean clay
  • Some construction debris and brick fragments were found in the samples
  • The water table was not encountered in any of the boring samples, nor evident in the holes within 24 hours after the samples were taken
  • Based on the location of some of the clays found, there is potential for water appearing and   dewatering will most likely be needed

 

General Site Preparation Suggestions

·        The existing clay and clayey soils should be removed from the site

·        The remaining sand should be stockpiled for reuse as backfill

 

Foundation Recommendations

·        The soil is quite capable of supporting a standard spread footing, but some of the underlying clay layers will most likely lead to some differential settlement

·        A deep foundation system is suggested to remove the effects of the underlying clay soils

·        Pressure injected concrete piles are suggested

·        Driven piles are not suggested due to the impact it may have on the existing structure

 

Excavation

·        The suggested shoring method for excavation support is sheeting and shoring

·        The depth of excavation ranges from 20 to 25 feet

·        The max effective stress value of 25 degrees and max cohesion of 150 psf is recommended for preliminary design of the sheeting and shoring system

 

Chemical Analysis

·        A geoprobe of the soils on site were taken to assess the presence of hazardous compounds within the soil

·        The test found the presence of arsenic, chromium, copper, lead, nickel, and zinc

·        The levels of contaminants found were low enough that the soil was classified as non-hazardous for disposal purposes

 

 

Technical Assignment #3

            The final technical assignment turns more towards a more focused look at certain aspects of construction.  There is a more detailed breakdown of the site with different layouts for the various phases.  A summary of the temporary utilities employed on the project, as required by the specification.  There is a detailed estimate requirement of a specific system in the building, in particular a system that will most likely be analyzed later on in the thesis.  There is a requirement for an in depth general conditions estimate.  The last portion is the proposed methods to be used in the research analysis in the Spring.

 

Alternate System and Methods Analysis          Monday November 15, 2004

·       Executive Summary  pdf

·       Site Layout Planning pdf

·       Temporary Utilities pdf

·       Detailed Systems Estimate  pdf

·       General Conditions Estimate  pdf

·       Research Analysis Methods pdf

 

 

Executive Summary:

            The submission of Technical Assignment Includes the Site Layout Planning with the three main phases:  Excavation, Erection, and Interior work.  There are minimal changes between the phases because the building is a renovation project.  The temporary Utilities are fairly simple because the contractor can use the existing power, water, etc, while the construction going on.  The Contractor does need to coordinate the switchover from existing to the new utilities in order to maintain operations.  The detailed systems estimate shows a large variation from the previous two estimates, mainly due to the unstated assumptions in the square foot and assemblies estimates that the building project is new construction.  Since the project is a renovation the detailed estimate takes into account the placement methods needed and therefore bears a higher cost of installation.  The general Conditions estimate worked out to be approximately 3% of the overall construction budget.  The research and analysis methods go into detail about the goals and objectives of the research and there is preliminary version of the survey to be used for the research.

 

Site Layout Planning

·        Excavation Site Plan features the Courtyard Excavation work

·        Erection Site Plan features the Erection Plan for the courtyard structure

·        Interiors Site Plan features the order of work throughout the interior of the building

 

 

Temporary Utilities

The use of the utilities required to run the renovation are somewhat unique because the building is a renovation project.  The specification section covering the use of the existing building states that when the existing utilities are not available for use, when they are being worked on and changed over, then the contractor should base their use from the specification section 1500. 

 

Use of the Existing Building

          The existing building must be maintained in a weather tight condition.  The use of     existing utilities is allowed until such time as they need to be removed to install new utility lines or replace the existing lines.  (Coordination of the change over is obviously the responsibility of the contractor.)  Permits must be obtained from Smithsonian Institution in order to perform welding and cutting, because the building is historic the owner wants to be aware of all work involving a potential fire.  Tools and equipment causing vibration must also request permission from SI before doing work due to the potential damage the vibration can cause to the Historic Building.  The chart below shows the limitations on the equipment to be used in the building.

 


Frequency

Maximum Peak

Particle Velocity

1-10 Hz

6mm/sec

10-40 Hz

6-13 mm/sec

40 Hz and above

13 mm/sec

 

Temporary Utilities

·        Temporary Utilities

·        Sewers and drainage

·        Water service, metering, and distribution

·        Sanitary facilities, including toilets, wash facilities, and drinking-water facilities

·        Heating and cooling facilities

·        Ventilation

·        Electric power service

·        Lighting

·        Telephone service

 

Since the building is very old, there are issues relating to the different expansion and contraction of materials due to changes in weather.  In order to limit the change in materials due to the temperature, the building is maintained at a relatively constant temperature using two (2) 40 ton temporary chillers and two heaters while it is under construction.  The project has not had to add separate services for electricity, sanitary or storm drainage.  All of those requirements are running from the buildings existing utility supplies and the systems have been coordinated so there is a direct switch-over from the old to the new system in all cases. 

 

Support Facilities

·        Temporary roads and paving

·        Wash racks

·        Dewatering facilities and drains

·        Project identification and temporary signs

·        Waste disposal facilities

·        Field offices

·        Storage and fabrication sheds

·        Lifts and hoists

·        Temporary elevator usage

·        Temporary stairs

·        Construction aids and miscellaneous services and facilities

 

Security and Protection Facilities

·        Environmental protection

·        Stormwater, sediment, and erosion controls control

·        Tree, plant, and animal protection

·        Pest control

·        Site enclosure fence

·        Security enclosure and lockup

·        Barricades, warning signs, and lights

·        Covered walkways

·        Temporary enclosures

·        Temporary partitions

·        Noise control

·        Weather protection

·        Fire protection

·        Existing storm water drains

 

Environmental Requirements:  Concrete Placement

Cold Weather concreting:

·        Frozen ground:  Do not place concrete on frozen ground.

·        Do not place concrete when temperature is below 40 degrees F, except with prior approval of Smithsonian Institution

·        Place concrete in cold weather in accordance with ACI 306.

Hot Weather concreting:

·        Do not place concrete when atmospheric conditions endanger quality of concrete.

·        Place concrete in hot weather in accordance with ACI 305.

·        Cover reinforcing steel with water soaked burlap if necessary to maintain steel temperature not exceeding ambient air temperature immediately before

·        embedment in concrete.

·        Use water reducing retarding admixture when concrete temperatures exceed 80 degrees F or other adverse placing conditions, as approved by COTR.

At time of placement, provide concrete temperature not lower than 50 degrees F, or higher than 90 degrees F. Maintain surfaces receiving concrete at approximately same temperature as concrete being placed.

 

Detailed Systems Estimate

 

 

 

Detailed Estimate Takeoff Notes for Concrete

          Below is shown the Concrete Takeoff for the courtyard.  Concrete is used in several capacities.  Obviously the slab on grade is concrete, the elevated slab is also concrete, though only half is structural two way while the other half is supported on steel beams.  The walls are structural concrete, 18” thick, and half of the columns in the Courtyard are also concrete.

 

 


Item

Dimension

Quantity

CIP Columns

14' Tall, 15" square

35

Steel Columns

18' Tall, 48 plf

24

Steel Columns

18' Tall, 58 plf

5

One Way Slab

30' x 6'

1

 

200' x 7'

1

 

20' x 40'

1

 

53' x 16

1

Total

 

3250 SF

Two Way Slab

80' x 43'

1

 

53' x 3'

1

 

33' x 6'

1

Total

 

3800 SF

Slab on Grade

 

7050 SF

W shape Beams & Girders

3250 SF

1

CIP Walls

18' x 53'

2

 

18' x 16'

1

 

14' x 75'

2

 

14' x 53'

1

Total

 

5000 SF

 

 


Concrete Columns (#)

Dimension 1 (in)

Dimension 2(in)

Height (ft)

CY

24

16

16

14

22.12

4

14

24

14

4.84

1

30

30

14

3.24

7

30

30

18

29.17

Total

 

 

 

65

 

 

 

 

 

Concrete Slabs

SF area

Depth (ft)

CY

 

SOG East Half

3800

0.42

58.64

 

SOG West Half

3250

0.67

80.25

 

Elev Slab East Half

3800

0.83

117.28

 

Elev Slab West Half

3250

0.67

80.25

 

Total

 

 

370

 

 

 

 

 

 

Concrete Walls

SF area

Depth (ft)

CY

 

 

5000

1.5

306

 

 

 

 

 

 

Total Amount of Concrete

 

 

741

CY

 

Detailed Estimate Takeoff Notes for Steel

          Below is the takeoff of the Courtyard’s steel structural system.  Steel is used for the   columns and beams in the Auditorium area of the courtyard which makes up a little less than half of the courtyard area. 

 

 


Steel Member

Quantity

Length (ft)

Total Length (ft)

Weight (lb)

Weight (Tons)

Columns

 

 

 

 

 

W 12 x

87

10

18

180

15660

8

W 12 x

120

18

18

324

38880

20

 

 

 

 

 

 

 

Beams

 

 

 

 

 

W 12 x

26

3

8

24

624

1

W 14 x

26

5

8

40

1040

1

W 16 x

26

4

10

40

1040

1

W 18 x

35

3

18

54

1890

1

W 21 x

50

5

13

65

3250

2

W 24 x

62

14

18

252

15624

8

W 30 x

116

2

30

60

6960

4

W 30 x

99

4

12

48

4752

3

W 38 x

120

9

64

576

69120

35

 

 

 

 

 

Total Weight

84

 

 

There is a large change in the cost of the structural system from the previous estimates.  In reviewing the differences I feel the reason for the increase in this estimate is the disparity of using the two separate structural systems has come out.  There is an inherent efficiency in using a single system for an entire structure.  By using two different systems for the east and west halves of the courtyard structure, there is an increased cost and increased time to construct.  Also, the fact that the courtyard is in the interior of a building being renovated was more evident because the placement methods for the steel and the concrete now were taken into account.  In the square foot and assemblies estimates there was an inherent assumption in the cost data that the building was new.  These two major items account for the majority of the cost differences from the two preliminary estimates to the current detailed estimate.

 

General Conditions Estimate

 

          The general conditions estimate was put together using MC2.  Areas where the specific costs and amounts were not known (permits, temporary storage, etc) a lump sum estimate was filled in using an educated guess of the amount needed for the project and a rough idea of the cost. 

          The general conditions estimate shows the major portion to be going into staffing for the job.  Since each of the superintendents and the project manager receive cars, those costs were built into the estimate as well.  There was no need to put money in for a site fence, one was already present.  There needed to be money for trailers, but because the site is very tight there is minimal room for trailers and not as many as would be typical of a project this size with more space.  Since there is limited space there needs to be money for staff parking offsite (travel expenses).  The project also requires regular progress photos. 

          Overall the estimate makes the cost of the general conditions around 3% of the job cost.  The percentage seems low for a typical project, however the size of the project throws off the relationship normal to a construction project.  Also, the program used to do the estimate uses salaries and some other costs that appear low based on the contractor performing the work.  The size of the project staff also creates different levels to the staff that can not easily be delineated in the estimating software. 

 

Research and Analysis Methods

Problem Statement:  There are no LEED registered art museums and a general lack of interest in green building from museums and similar facilities.  Green building is a theme that should be universal in construction and arts' centers would be a large stepping stone in

convincing people green building is not just a small niche in the market.  Since most buildings are not toured on a regular basis by large numbers of people, it is rare for the advantages of green building to be showcased to the public.  Integrating green design and construction into a building aimed to showcase and teach the public is an ideal setting for demonstrating the value green techniques can bring to a building.

 

Goals:  Showing LEED certification is not only viable but advantageous for museums and arts centers would go a long way to show green building is practical in almost all facility types.  To properly show LEED as being viable it is necessary to pinpoint the challenges for these building types and show how they can be overcome or alternative systems which will fulfill the requirements and be better for the environment. 

 

Objectives:

1. Literature Review

1.    Read 12 relevant and current articles on issues with greenbuilding

2.    Review of LEED Point system and narrow down the areas of the system that are most challenging for museums and arts’ centers.

3.    Talk/email with the design manager from Smithsonian Institution at the    Patent  Office Building and see what concerns they have with LEED and why more environmentally friendly systems and techniques were not used.

4.    Talk w/ Penn State Office of Physical Plant Project Manager to gain some insight the differences between a museum facility and a regular classroom facility and the challenges with applying LEED to an arts’ center.

 

2. Study

1.    Analysis of points areas for museums to focus

2.    Develop Reasoning behind museums as next logical step for LEED

3.    Study similar facilities and arts’ centers which are close to meeting LEED requirements

4.    Review market data for LEED from USGBC website and analyze for points aimed at by different building types

 

3. Outcome  - review data and show if museums should go green

1.    Show challenges specific to museums/arts’ centers

2.    Demonstrate via similar building types and answers to interview questions that Art Museums have equal opportunity and reasons to go green/LEED

 

4. Future Research - find shortcomings of research and new areas and ideas created by outcomes

1.    Show two areas of research shortcomings with potential for further research

2.    Show three new areas opened up by the research for further study

 

 

Interview Questions

Opening Statement:  LEED is a growing portion of the building market.  Thus far there are no LEED registered art museums and a general lack of interest in green building from museums and similar facilities.  Arts' centers would be a large stepping stone in convincing people that green building is not just a small niche in the market.  Since most buildings are not toured on a regular basis by large numbers of people, it is rare for the advantages of green building to be showcased to the public.

 

Unstructured Interview:  Smithsonian Institution

1.    What is Smithsonian’s take on the LEED point systems and does Smithsonian plan on using it on any projects in the near future?

 

2.    What special concerns does a museum have which will make building a LEED certified  facility especially challenging?

 

3.    What reasons are most appealing to SI for having a LEED certified building?

 

4.    What issues might affect an art museum from attaining points in the following areas:

·        Sites?         (access  -  loading/unloading of exhibit items)

 

·        Water?      (chemicals used in restoration, green roof)

 

·        Energy?    (requirements for maintaining painting quality, daylighting)

 

·        Materials? (low VOC’s, recycled materials, regional materials)

 

Structured Interview:  Office of Physical Plant at Penn State

1.    What are the key reasons Penn State has started building LEED certified buildings?

 

2.    What special concerns does a museum have which might make building a LEED certified facility challenging?

 

3.    Penn State has decided to build LEED certified buildings, are there any building types where the possibility of LEED is discounted, and why?

 

4.    What issues might affect an art museum from attaining points in the following areas:

·        Sites?         (access  -  loading/unloading of exhibit items)

 

·        Water?      (chemicals used in restoration, green roof)

 

·        Energy?    (requirements for maintaining painting quality, daylighting)

 

·        Materials? (low VOC’s, recycled materials, regional materials)

 

 

 

 

 

This page was last updated on Monday, January 24, 2005.

This page was created by Robert M. Leicht and is hosted by the AE Department.