Andrew Solomon

Structural

M. Kevin Parfitt

Willow Valley Health Center

850 Willow Valley Lakes Drive

Willow Street, PA

September 9th, 2005

 

WILLOW VALLEY HEALTH CENTER
BUILDING STATISTICS

 

PROJECT TEAM

 

Owner...................................................... Willow Valley Retirement Community, Inc.

                                           850 Willow Valley Lakes Drive

                                           Willow Street, PA

 

Designer/Builder........................... Paul Risk Associates, Inc.

                                           Quarryville, PA

 

Architect................................................ Bernardon Haber Holloway Architects

                                           Kennett Square, PA

 

Structural Engineer....................... Baker Ingram and Associates

                                           Lancaster, PA

 

Mechanical Engineer................... Protech Mechanical Contractors

                                           Landisville, PA

 

Electrical Engineer........................ Haller Enterprises

                                           Lititz, PA

 

Civil Engineer.................................... RGS Associates

                                           Brownstown, PA

 

Interior Designers......................... JSA Architects

                                           Portsmouth, PA

 

Food Service Designer............... Clark Food Service

                                           Lancaster, PA

 

Geotechnical Consultants...... CVM Industries

                                           Huntington Valley, PA


SITE & BUILDING

 

The site chosen for the new Willow Valley Health Center is located in a relatively new and developing retirement community.  This community is located approximately 5 miles south of the heart of Lancaster on route 222.  This is a perfect location because this building will act similar to a nursing home where not all of the tenants are fully capable of taking care of themselves but the ones who are allowed to be left unsupervised can travel into the borough. 

 

CONTSTRUCTION

 

$11.8 Million is the estimated total owner cost in which Paul Risk and Associates presented to the owners on this Design-Build project.

 

Construction started on May 15th, 2005 and is expected to commence by April 1st, 2006

 

Willow Valley Health Center is approximately 118,400 square feet.  This includes 4 stories above ground with a partial basement.

 

 

ARCHITECTURE

 

A two toned brick façade with mansard/false gabled shingle roof was used on this building to complement the existing buildings in Spring Run.  There are three wings to this Y shaped building and each wing is anchored on the building end with a hipped roof tower.  False windows were added to some of the towers to minimize the amount of blank exterior walls.  A Porte-cochere is to be added at the grand entrance to allow for a tour bus to pass through.

 

The entrance is to act as a “grand hotel” entry lobby with a two story atrium.  The first floor public thoroughfare (from entry to dining room) is designed to reflect as a retail “main street” to the residents and visitors with access to dining, café, administration, rest rooms, library, mailroom, and lounge areas.

 

IBC 2003 was used in the design of this building along with local codes and zoning restrictions.  The height restriction was exceeded so to fall back into code, the designers were forced to shift the footprint.  The zoning setbacks on the North and South boundaries forced the architect to be creative.  After the building moved, redistribution of parking spaces had to be approved again.  The deletion of an originally planned parking garage made this a bigger issue.  I am still waiting on a reply from the owner’s rep

 

During excavation, bedrock levels varied greatly from that of the geotechnical surveys.  This caused a combination of blasting/over-excavation/stone column work in order to get a class A rating. 

 

Because of the complications with this project and zoning, 3 different architects were utilized and the project was reviewed by the township two times.

 

The building site is original zoned R-3 (Medical/Residential).  The final land plan was approved after going through a second conditional use hearing but it had 22 conditions attached.  This is a significant amount of conditions for such a small building.

 

PRIMARY BUILDING SYSTEMS

 

Construction Method – Paul Risk and Associates was hired by the owner to supervise the design and construction of the building.  It is a design build project with little prefabricated structural elements.  This is important to Paul Risk because they can order material on an as-needed basis.  I am waiting to hear from the contractor on any more special construction means or methods.

 

Structural System – The 8” load bearing reinforced masonry walls are also the shear resistance for the building.  The floors and roof are comprised of pre-cast concrete plank flooring along with a topping to make for a smooth surface.  The use of a pre-cast floor system limited the distance of spans to 30 feet.  There are steel columns where a masonry wall or pier is not feasible.  The load bearing masonry walls rest upon wall footings while the steel columns are supported by spread footings.

 

Electrical - Willow Valley Retirement Community, Inc. owns their own primary electric grid on their properties.  All buildings are supplied with 480/277volt secondary services.  Electrical systems within the buildings are pretty standard; power, lighting, fire alarm, communications, data, and sound systems. Emergency power generation is provided through diesel and natural gas powered generators.

 

Lighting – The typical lighting system in the building is 48” florescent lamps in 2’x4’ light fixtures which are going to fit into the suspended ACT ceiling. 

I am waiting to hear from the contractor about the use of any special lighting anywhere in the building.  From previous conversations he implied he did not know of any but is going to talk to someone who would know more.

 

Mechanical - Most buildings in this area are served by a water source heat pump system.  This system uses a closed loop of circulated water to serve as the primary heat exchange media for both cooling and heating seasons. Heat is rejected from the loop with an outdoor cooling tower; heat is introduced to the loop through a gas boiler depending on the building demand for cooling or heating. This system is very efficient for large, full time occupied buildings such as apartments.

 

 

SECONDARY BUILDING SYSTEMS

 

Telecommunications - A communications duct bank parallels the primary electric grid throughout the property.

 

Transportation – There are two elevators located near the main lobby/grand entry along with 1 stairwell at the end of each wing.

 

Fire Protection – there are both passive and active fire protection systems.  All masonry walls act as a fire wall and the pre-cast concrete floor planks contain their own fire rating.  There is a full sprinkler system in all parts of the building to suppress a fire.