The Millennium Science Complex, located on The Pennsylvania State University campus in University Park, PA, is a 275,600 square foot, four-level, state-of-the-art research and lab facility. It is set to house the Huck Institutes of Life Sciences and the Material Sciences, and is scheduled for completion in the summer 2011. The building’s signature feature is a 150-foot cantilever which extends from the connection of the two wings at the main entrance. The building also includes several green roofs, which help the project achieve LEED certification. Additionally, the Millennium Science Complex contains 20,000 square feet of vivarium space, 40,000 square feet of quiet lab space, and 9,500 square feet of nano-clean room space. |
Note: While great efforts have been taken to provide accurate and complete information on the pages of CPEP, please be aware that the information contained herewith is considered a work‐in progress for this thesis project. Modifications and changes related to the original building designs and construction methodologies for this senior thesis project are solely the interpretation of Thomas Villacampa. Changes and discrepancies in no way imply that the original design contained errors or was flawed. Differing assumptions, code references, requirements, and methodologies have been incorporated into this thesis project; therefore, investigation results may vary from the original design.
This page was last updated on May 1, 2011, by Thomas Villacampa and is hosted by the AE Department © 2010. |
Capstone Project Description: The Capstone Project Electronic Portfolio (CPEP) is a web‐based project and information center. It contains material produced for a year‐long Senior Thesis class. Its purpose, in addition to providing central storage of individual assignments, is to foster communication and collaboration between student, faculty consultant, course instructors, and industry consultants. This website is dedicated to the research and analysis conducted via guidelines provided by the Department of Architectural Engineering. For an explanation of this capstone design course and its requirements, click here. |
CPEP Website Complete and Ready for Final Review |
5.1.11 |
ABET Assessment and Reflection Posted |
5.1.11 |
4.15.11 |
|
4.8.11 |
|
Discussion Board Question Posted |
2.11.11 |
1.21.11 |
|
1.14.11 |
|
1.13.11 |
|
BIMception Schematic Design and Construction Planning Report Posted |
1.13.11 |
1.13.11 |
|
1.12.11 |
|
Building Statistics Part 2 - Posted on CPEP |
1.12.11 |
Proposal Submitted |
12.6.10 |
BIMception BIM Execution Plan Submitted |
11.15.10 |
BIMception Schematic Design and Construction Planning Report Submitted |
10.27.10 |
CM Existing Conditions Report Submitted |
10.4.10 |
Abstract Submitted on Display Board |
10.4.10 |
Abstract Color and Content - Paper Draft |
9.24.10 |
Building Statistics Part 1 - Posted on CPEP |
9.13.10 |
Resume Submitted for AE Career Fair Listing |
9.13.10 |
Resume Posted |
9.13.10 |
Bio Sketch Posted |
9.13.10 |
CPEP Website - Full Menu Functional |
9.3.10 |
Building Statistics Part 1 - Paper Draft |
9.3.10 |
CPEP Home Page Draft |
9.3.10 |
Career Fair Hosting Sign Up Complete |
8.27.10 |
Discussion Board Confirmed |
First week |
Attended CPEP Seminar |
8.26.10 |
Confirmed Master List Info |
8.23.10 |
Obtained Project Documentation |
First Week |
Owner Permission Received |
Summer |