Note: While great efforts have been taken to provide accurate and complete information on the pages of CPEP, please be aware that the information contained herewith is considered a work‐in‐progress for this thesis project. Modifications and changes related to the original building designs and construction methodologies for this senior thesis project are solely the interpretation of Matthew Moore. Changes and discrepancies in no way imply that the original design contained errors or was flawed. Differing assumptions, code references, requirements, and methodologies have been incorporated into this thesis project; therefore, investigation results may vary from the original design.
|
|
|  |
Research
The research that was done for this thesis is on Short Interval Production Scheduling, (SIPS). Within this document you will find background on SIPS and well as the methodology about how to develop a successful schedule. It describes that step by step process which will guide you to developing a SIPS:
- Break the operation into specific activities
- Assign production rates to each activity
- Calculate extensions and set goals
- Develop a time-scaled, resource loaded bar chart
|
|