August 1, 2008
Here you can see the 7th floor is being poured. Exterior sheathing has been attached at the lower floors, in preparation for attaching the EIFS.
____________________________________________________________________
July 1, 2008
Making progress - 4th floor pour. Here the sequence of pours is quite obvious. Formwork can still be seen on the left hand side indicating a West to East sequencing in three separate pours. The elevator core can also be seen at the center of the building.
May 12, 2008
First floor columns and shear walls have been placed and you're starting to see the slab on grade.