|
Building Information |
Building Name: |
New Regional Medical Center |
Location: |
East Norriton, PA |
Function: |
Medical Hospital |
Primary Occupant: |
Institutional Group I-2 |
Accessory Occupancies: |
A-2, S-2 |
Gross Area: |
366,780 SF |
Number of Stories: |
5 Stories |
Construction Dates: |
7.6.2010 - 8.31.2012 |
Contrated GMP: |
$147 million |
Delivery Method: |
CM at Risk |
|
Code Requirements |
International Building Code 2006 |
International Existing Building Code 2006 |
ICC Electrical Code 2006 |
International Fuel Gas Code 2006 |
International Mechanical Code 2006 |
International Plumbing Code 2006 |
International Performance Code for Buildings & Facilities 2006 |
International Fire Code 2006 |
NFPA (Life Safety Code) 2000 Edition |
International Energy Conservation Code 2006 |
|
Zoning Requirements |
Exit Access & Travel Distances |
Institutional: I-2 |
200 Feet |
Assembly: A-2 |
250 Feet |
Storage: S-2 |
400 Feet |
|
Maximum Allowable Height |
75 Feet + 20 Feet (Sprinkler) |
95 Feet |
|
Maximum Allowable Stories |
4 Stories + 1 Story (Sprinkler) |
5 Stories |
|
Fire Rating (Type 1B) |
Structural Frame* |
2 Hours |
Exterior Bearing Walls |
2 Hours |
Interior Bearing Walls |
2 Hours |
Floor Construction |
2 Hours |
Roof Construction** |
1 Hour |
* Fire resistance rating to be reduced 1 hour where supporting roof only. |
** No fire protection is required for roof structural members where all roof elements are 20 feet or more above any floor below. |
|
Historical Requirements |
This building has no historical requirements. |
|
Image Gallery |
|
![](Building Images/South Elevation - West.JPG) |
Figure 5 | South Elevation - West Wing |
|
|
|
|
![](Building Images/South Elevation - East.JPG) |
Figure 6 | South Elevation - East Wing |
|
|
|
|
![](Building Statistics/Building Statistics 1/Facade.JPG) |
Figure 7 | Curtin Wall |
|
|
|
![](Building Images/Metal Panel.JPG) |
Figure 8 | Metal Panel |
|
|
|
![](Building Images/Roof Image.JPG) |
Figure 9 | Roof Image |
|
|
|
![](Building Images/Leed.jpg) |
Figure 10 | USGBC |
|
|
|
Project Team Directory |
Owner |
![](Building Statistics/Project Team Logos/AEMH Partnership.PNG) |
New Regional Medical Center, Inc. |
Construction Manager |
![](Building Statistics/Project Team Logos/Gilbane Building Company.png) |
Gilbane Building Company |
Architect |
![](Building Statistics/Project Team Logos/Perkins_Will.png) |
Perkins + Will |
Structural Engineer |
![](Building Statistics/Project Team Logos/O'Donnell_Naccarato.png) |
O'Donnell & Naccarato |
Civil Engineer |
![](Building Statistics/Project Team Logos/Bohler Engineering.png) |
Bohler Engineering |
MEP & Fire Protection Engineer |
![](Building Statistics/Project Team Logos/PWI.png) |
PWI Engineering |
Traffic Engineer |
![](Building Statistics/Project Team Logos/TPD,Inc 2.png) |
Traffic Planning & Design, Inc. |
Landscape Architect |
![](Building Statistics/Project Team Logos/Wells Appel.PNG) |
Wells Appel |
|
Location & Site |
559 West Germantown Pike, East Norriton, Pennsylvania, USA |
|
![](Building Statistics/Building Statistics 1/Regional Map.PNG) |
![](Building Statistics/Building Statistics 1/Local Map.PNG) |
Figure 1 | Regional Map |
Figure 2 | Vicinity Map |
|
The site of the New Regional Medical Center is an 84-acre Greenfield property. Previously occupied by an 18-hole golf course, miniature golf course, and auxiliary buildings, this site provides a very accessible and open plan for development. It is located directly off of a main arterial road (Germantown Pike) which bisected half of Montgomery County, and provides access to major roadway systems of neighboring counties, as shown in Figures 1 and 2. The site design shall preserve over one-third of the property as open green space for patients, visitors, and public walking trails. Directly across Germantown Pike (to the South) is the Norristown Farm Park, a Pennsylvania State Park, which includes a working farm surrounding the grounds of the former Norristown State Hospital, as seen in Figure 3. Additional property boundaries include residential development (North and East), and Whitehall Road (West). Along Germantown Pike, on the Southwest and Southeast corners of the property, there are existing establishments that range from restaurants, drugstores, and retail services, as shown in Figure 4. |
![](Building Statistics/Building Statistics 1/Aerial Map.PNG) |
![](Building Statistics/Building Statistics 1/BirdsEye Map.PNG) |
Figure 3 | Aerial Map |
Figure 4 | Birds-Eye View |
|
|
Architecture |
Design |
The architectural design of the New Regional Medical Center includes five stories of medical services, encompassing over 366,000 gross square feet. When viewing the design in plan, the building is broken out into two sectors, the patient tower to the south, and the CUP, medical surgery, and emergency services to the north, as shown in Figure 5. The first two levels are full service floors, while the second, third, and forth floors are reserved for patient rooms, and the floor size is reduced to create the patient tower. The main architectural feature of the project is the five story central patient tower atrium. This atrium serves as the location of the main entrance, and the vertical conveyance systems for the hospital. It also provides a sun-filled space, in which each floor's balcony steps back away from the curtain wall to provide an open, large, panoramic view of the surrounding green space. |
Function |
The New Regional Medical Center includes 146 beds: 96-bed medical/surgical, 22-bed intensive care unit, 20-bed obstetrical unit, and an 8-bed neonatal intensive care unit. It also includes a state-of-the-art 24 hour emergency department, advanced cancer care, advanced cardiac services, in addition to cutting-edge catheterization and electro-physiology laboratories. Future campus development includes direct on-site access to primary care at the adjacent Medical Office Building. |
|
Building Enclosure |
Facade System |
Curtain Wall System |
As shown in Figure 7, the primary building enclosure is a curtain wall system which incorporates precast panels and glazing units. The subsections below will detail each component in this assembly. |
Precast Panels |
The architectural precast concrete panels are located on the North, South, and East facade of the patient tower. They are comprised of a mix of 50% gray cement and 50% white cement in the face mix. The panels contain both face-mixture-coarse aggregates and face-mixture-fine aggregates. In order to create aesthetic variation across the surface, light sandblasting occurred on specific sections, while heavy sandblasting occurred on others. |
Glazing |
The window systems included in this curtain wall system consist of 10 different types. Vertical mullions are either 7.5" or 10.5" deep, while the horizontal mullions are 2.5", 7.5", or 10.5" deep. Glass components vary per window type, and include horizontal structural glazing, two way structural glazing, and four way structural glazing. Each pane is mechanically framed with gaskets on four sides. |
Block Face |
Split-faced concrete masonry units are located on the building at the West, North, and East sections of exterior wall at the Emergency Department and the Central Utility Plant. This change from curtain wall to a block face complements the architectural change from 5 floor patient towers to the two floor medical surgery and emergency departments. |
Metal Panel |
Metal panel components are located on the building at the West facade of the patient tower in addition to the screen wall surrounding the rooftop mechanical systems for the low roof. A detail of this component is shown in Figure 8. |
Facade Mockups |
Onsite mockups were developed to verify structural connections, flashing, joint caulking, and material selections for the various façade systems incorporated in the New Regional Medical Center. |
|
Roofing System |
Roof System 1 (RS-1) |
Roof System 1 consists of a complete Thermoplastic-Polyolefin (TPO) assembly. The components of this assembly include flashing, roof sheathing, vapor barrier, 4 inch thick rigid insulation (tapered at select locations), exterior sheathing, and single ply TPO membrane of RFG-1 (60 mils) adhered over metal deck. |
Roof System 2 (RS-2) |
Roof System 2 consists of a complete TPO assembly. The components of this assembly include flashing, roof sheathing, vapor barrier, 4 inch thick rigid insulation (tapered at select locations), exterior sheathing, and single ply TPO membrane of RFG-2 (80 mils) and gravel ballast over concrete over metal deck. |
Roof System 3 (RS-3) |
Roof System 3 consists of a complete TPO assembly. The components of this assembly include flashing, roof sheathing, vapor barrier, 4 inch thick rigid insulation (tapered at select locations), exterior sheathing, and single ply TPO membrane of RFG-2 (80 mils) and gravel ballast over metal deck. |
Roof System 4 (RS-4) |
Roof System 4 consists of a complete TPO assembly. The components of this assembly include flashing, roof sheathing, vapor barrier, 4 inch thick rigid insulation (tapered at select locations), exterior sheathing, and single ply TPO membrane of RFG-1 (60 mils) adhered over metal deck. |
Roof System 5 (RS-5) |
Roof System 5 consists of a single ply TPO membrane of RFG-1 (60 mils) over sheathing and metal deck/structure. |
Roofing Details |
Roof Sheathing |
5/8 inch thick |
Vapor Barrier |
minimum 6 mils thick | maximum 0.13 perm permeance rating |
Roof Insulation |
Rigid, closed-cell, complies with ASTM C578 Type VI |
Compressive strength of 40 psi |
|
Exterior Sheathing |
5/8 inch thick |
Roof Ballast |
Aggregate Type: Smooth, washed, riverbed gravel |
Size: ASTM D 448, Size 2 (1.5” - 2.5”) |
|
|
|
|
Sustainability Features |
LEED Certification |
Land Preservation & Waste Management |
CFD & Energy Analysis Modeling |
Site Layout & Solar Gain |
HVAC & Lighting Controls |
Operating Room Air Handling |
Future Technology Consideration |
|
|
The New Regional Medical Center is dedicated to implementation of sustainability features within design, construction, and lifecycle of the facility. With consideration for the patients, the community, and the environment, countless steps have been taken by the Einstein-Montgomery Partnership and project team to achieve their goal of a LEED Certified rating for the medical campus. |
|
Due to the project's Greenfield site, a major goal of the project is land preservation. Through thoughtful design, 30 acres of the 84 acre site will be preserved, and low-maintenance landscaping and public walking trails will be included to reflect the Norristown Farm Park and surrounding region. The construction management team is to coordinate recycling, disposal and waste management during construction, with a goal to recycle 75% of construction waste. Strategic building placement by the design teams enables the facility to take advantage of solar gain and maximize the use of natural sunlight and thermal storage capacity. Due to the influence of selected building materials, color and placement, the design staff is able to capture the natural environment and reduce energy expenses. The operating rooms are serviced through 100% outdoor air, with a heat recovery program to assist in a building-wide energy efficient mechanical system. The designed system is 14% more efficient then required by code. LEED featured designs also incorporate Computational Fluid Dynamic (CFD) and Energy Analysis models, which assist in indoor air quality and energy management. For example, the Smoke Management system for the 5 story Atrium was developed through a CFD model, ensuring high performance and operability. Also, the majority of lighting fixtures in the building incorporate energy efficient compact fluorescent lights. Sustainable design development was also included for future technology. For example, the engineering design incorporates additional items consistent with LEED certification requirements, such as the addition of active solar photovoltaics, and a comprehensive building energy model. |
|
To ensure compliance with all LEED requirements, the construction manager shall retain an independent and dedicated LEED Compliance Administrator to handle all LEED documents and project controls during construction. In addition to this, a third party commissioning agent will facilitate verification that energy related components meet the owner's needs and project requirements per the contract documents. |
|
|
|