Prototype 1: May 1999 - Crow Reservation, MT |

|
Plan
load bearing walls
interior framed walls |
Cost
$35,000 Total cost
$28/SF Material cost
24% Contracted work |
Section
1.5 Story
28' Span trusses |
Schedule
27 Day shell and core
15% Semi skilled labor
85% Skilled labor |
|
Prototype 2: July 2000 - Lakota Reservation, SD |

|
Plan
load bearing walls
interior utility core
interior straw wall |
Cost
$40,000 Total cost
$30/SF Material cost
17% Contracted work |
Section
1 Story
32' Span trusses |
Schedule
14 Day shell and core
35% Semi skilled labor
65% Skilled labor |
|
Prototype 3: July 2001 - Northern Cheyenne Reservation, MT |
 |
Plan
load bearing walls
interior utility core
interior straw walls |
Cost
$63,000 Total cost
$45/SF Material cost
16% Contracted work |
Section
1 Story
36' Span trusses |
Schedule
21 Day shell and core
38% Semi skilled labor
62% Skilled labor |
|