| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Building Statistics |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Architecture RGA Global Headquarters embodies flexibility and presence. Below grade is a two story concrete parking garage, exposed on the lower side of the site, giving rise to two identical, five story office buildings. An amenities level on the first floor of the complex connects the office buildings with the upper floors which are cantilevered over the amenities level. The "floor plates" of the office buildings exhibit an open floor plan that maximizes circulation and planning flexibility. Along the longitudinal axes of the offices is a series of service cores for mechanical systems, restrooms, elevators and stairs. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Zoning C-8: Planned Commercial District Historical Requirements Not Applicable |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Building Envelope The roofing system consists of a single ply Thermoplastic Polyolefin Sheet (TPO) membrane that complies with the LEED Solar Reflectance Index requirement. Additional insulation in the form of a cementitious fill material and Expanded Polystyrene (EPS) is provided. This roofing system is supported on composite acoustical deck system. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Sustainability Features RGA Global Headquarters has a project goal and design basis of achieving LEED Silver Certification. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Structure Superstructure: The two office tower structures are constructed A992 grade 50 steel. The floors are 3 inch composite metal deck with 3 1/2 inch semi-lightweight concrete topping of 3000 psi. Typical gravity beams are W14x22, W16x26, W18x35, W21x44, W21x50, and W24x62 with cambers of 3/4 inch to 1 3/4 inch. Roof construction is 3 inch 20 gage type N roof deck with roof beams of W21x57, W21x44, W12x19, and W8x18 with cambers 3/4". Gravity columns on lower levels are larger, typically W10x49, W12x65, W12x79, W12x87, W12x136 while smaller on upper levels, typically W12x65, W12x58, W12x53 with the column splices occurring 4 ft. above Level 04. The 40 ft., four floor cantilever is supported by a truss system with the compression columns bearing on a 4 ft. deep plate girder spanning between them. On the roof level where the top of the tension members meet the roof beams the beams are designed to take axial tension, which decreases further away from the cantilever. (More details are available in Technical Report 1). Substructure: Foundation: Lateral System: |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Construction RGA Global Headquarters is a $150 million design-build project. The complex is approximately 405,000 gross square feet and has a finish elevation above grade of 85 ft. There are no strict height limits, existing utilities, or previous construction associated with the existing site. Five of its stories are completely above ground and two stories are built into a hill. Construction on the project began in March 2013 and will continue until September 2014. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electrical The mechanical equipment and lighting fixtures run on 480/277 volt system while the office receptacles step down to a 208/120 volt system. Electricity is fed by 3-phase, 4 wire buses into four main switch boards which are rated for 3000 amperes. The Core and Shell design supplied panelboards rated for 100, 225, 400, 600 and 800 amperes. Finally, emergency and standby equipment in the complex is supported by diesel engine generators. Tennant fit out design for interior electrical is currently in progress and information will be posted as it becomes available. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Lighting Most exterior and all emergency lighting is LED lamps and assorted fixtures. Walkway lighting is utilizes recessed and handrail fixtures while the parking lot fixture is a gantry light pole. Uplighting is accomplished with fluorescent lamps having both electronic and magnetic ballasts. Exterior lighting and interior restroom lighting run on a 277 volt system. Tennant fit out design for interior lighting is currently in progress and information will be posted as it becomes available. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Mechanical Core and Shell: The mechanical system for the complex is designed for year-round cooling. This cooling is supplied by three cross flow cooling towers which service three, 650 ton water cooled chiller units. Two 60,000 CFM air handling units service each office tower and four others of various sizes serve various segments of the amenities spaces. Office tower AHU’s are located in a mechanical penthouse on the roof of each tower. Air is supplied to each floor of the offices by a medium pressure loop with VAV branch capability as needed for the interior fit out. Additionally, three fan powered terminal units in each office tower provide heat to the floor cavity of the outlook cantilever to counteract the space’s potential for a heat sink. Finally, all of these components are integrated into the complex's Building Automation System (BAS). Interior: |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Fire Protection The design follows the fire protection requirements set by the International Building Code (IBC) and by the National Fire Protection Association (NFPA). The complex is fully sprinkled with a wet pipe sprinkler system and has smoke and heat detectors both in the public spaces and the HVAC ducts. The BAS is also encoded with the necessary fire protection protocols. The fire protection system itself is a Remote Station Protective Signaling System meaning that when an alarm is triggered it is transmitted to a remote location usually over a telephone wire to alert fire authorities. This type of system is typical for private offices and buildings that spend extended periods unoccupied. Fire ratings needed in the design were one hour roof construction and two hour floor construction, structural members, and stair and elevator shafts. Between the lower amenities levels and the parking garage required a three hour fire separation for all walls and doors. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Transportation Tennant fit out design for interior telecommunications is currently in progress and information will be posted as it becomes available. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Telecommunication Tennant fit out design for interior telecommunications is currently in progress and information will be posted as it becomes available. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Note: While great efforts have been taken to provide accurate and complete information on the pages of CPEP, please be aware that the information contained herewith is considered a work-in progress for this thesis project. Modifications and changes related to the original building designs and construction methodologies for this senior thesis project are solely the interpretation of Natasha Beck. Changes and discrepancies in no way imply that the original design contained errors or was flawed. Differing assumptions, code references, requirements, and methodologies have been incorporated into this thesis project; therefore, investigation results may vary from the original design. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
This page was last updated on 10/24/13, by Natasha Beck and is hosted by the AE Department ©2014 |