Welcome to Nate's AE Senior Thesis e-Portfolio
Progress Log
Date | Announcement |
04.12.06 | Thesis Presentation posted |
04.06.06 | Final Report updated |
04.03.06 | Final Report posted |
01.16.06 | Schedules posted in Progress Log |
01.16.06 | Proposal revisions posted |
01.11.06 | Breadth revisions posted |
12.09.05 | Thesis Proposal posted |
11.21.05 | Tech 3 and Executive Summary posted |
10.31.05 | Tech 2 posted, Executive Summary posted |
10.10.05 | Tech 1 Executive Summary posted |
10.05.05 | Tech 1 posted |
09.25.05 | Thesis Abstract posted |
09.19.05 | Building Statistics posted |
09.14.05 | Created e-portfolio webpage |
08.31.05 | Started 5th year classes |
Planning Schedule
- January
- 12 - Learn BLCC4
16 - Updated Proposal Due
17 - Parallel Systems
30 - Run-Around Heat Recovery System
31 - Progress Check
February
- 06 - Guest Rooms IAQ
20 - Lighting Breadth Work
27 - Acoustics Breadth Work
28 - Progress Check
March
- 13 - System Integration and Comparisons
15 - Table of Contents
20 - Finish All Unresolved Issues
27 - Write Final Report
April
- 03 - Final Report Due
10 - 1st Round of Presentations
28 - AE Banquet
Detailed Schedules
To view the Detailed Schedule for entire semester, please click here.
To view the Detailed Schedules for each month, please click on the following links.