Technical Assignments

 

Technical Assignment 1 - ASHARAE Standard 62.1-2004 Compliance Evaluation.

The ventilation rates for the Straumann USA facility were analyzed for compliance with ASHRAE Standard 62.1-2004 using the prescriptive ventilation rate procedure.

Executive Summary

Full Report

Technical Assignment 2 - Building and Plant Energy Analysis Report

Straumann USA was analyzed to determine the number possible LEED points generated and compliance with ASHRAE-Standard 90.1-2004. A building load and cost estimate was performed and compared to the design loads and actual building energy costs.

Executive Summary

Full Report

 

Technical Assignment 3 - Mechanical Systems Existing Conditions Evaluation

The current mechanical systems of Straumann USA were analyzed along with the control strategies that were implemented. Included with the report are schematic drawings of the major systems of the building.

Executive Summary

Full Report

 