Progress Log - Spring 2006

------------------------------------------------------

I have, for your pleasure, a calendar of the semester outlining my thesis work schedule. While I anticipate it will not go even nearly as well as planned, it provides an overview of what I plan to accomplish for my final presentation. I am even going to post a calendar of the whole month of January and the activities therein.

**Edit: You may notice that the schedule has been shifted already to make room for the interview schedule I had planned. For this reason, everything got slightly backed up, but will be on track fairly soon. Posting of progress will continue throughout the semester, so check back.

January Calendar - (15KB)

Semester Schedule - (11KB)

------------------------------------------------------

All other activites throughout the Spring semester took place sporadically, and then in variable fashion (i.e. no task was specifically completed with another beginning, but all of them started and finished in hodge-podge order). The last four weeks of thesis (three days before the end of Spring Break - March 9th - and ending the day of my presentation - April 10th) contained workdays anywhere between 8 hours and upwards of 24 dependent on the task and proximity to the "due date". Any inquiry regarding specific activities can be made to Steven Puchek at stp140 with the typical @psu and the .edu.

 

Progress Log - Fall 2005

 

Recent Developments (newest first)

Date Event Comments
12.09.05 Thesis Proposal Depth, Breadth and Schedule Draft Submitted
12.08.05 Tech 3 - Schematic Lighting Design Final PPT and Executive Summary Posted
12.08.05 Website Revision v2.4
12.07.05 Self Evaluation and Grading Completed in class with MKP
12.06.05 Tech 3 - Schematic Lighting Design Presentation at Lutron
12.04.05 Tech 3 - Schematic Lighting Design Alter PPT, add Equipment, Alter Sketches
12.02.05 Interior Development - Arch 496 Final Materials and Layout Meeting
11.30.05 Tech 3 - Schematic Lighting Design Revision Meeting for Lutron Presentation
11.28.05 Tech 3 - Schematic Lighting Design Compiled, Submitted, Posted
11.28.05 Website Revisions v2.0
11.26.05 Tech 3 - Schematic Lighting Design Additional spaces (Arch 496) Added
11.21.05 Tech 3 - Schematic Lighting Design Draft Submitted
11.18.05 Interior Development - Arch 496 Materials Development and Omni Illumination for Tech 3
11.11.05 Tech 3 - Advisor Meeting Dr. Moeck to Discuss Metaphor and Scheme
11.04.05 Interior Development - Arch 496 3d Development for Circulation, Full-height Partitions, etc.
10.31.05 Tech 2 - Existing Electrical Conditions Submitted and Posted
10.28.05 Tech 3 - Second Meeting Metaphor and Scheme Development
10.21.05 Interior Development - Arch 496 4-story floorplate layout development complete
10.19.05 Tech 3 - Preliminary Meeting Metaphor and Scheme Development
10.18.05 Meeting - Electrical Consultant Ted Dannerth - Electrical Questions with Tech 2
10.14.05 Tech 1 - Existing Lighting Conditions Resubmitted and Reposted
10.13.05 Website Revisions v1.0
10.11.05 Thesis Abstract Posted Submitted and Posted
10.11.05 Website Revisions v0.3
10.10.05 Bio-Sketch Submitted and Posted
10.10.05 Contact A&O WE Energies Contact for Xmfr Vault
10.07.05 Tech 1 - Existing Lighting Conditions Received, Major Revisions Begun
10.05.05 Tech 1 - Existing Lighting Conditions Draft Submitted and Posted
10.03.05 Contact Lurie Glass Mark Lurie - Glass Specs
9.30.05 Meeting - Electrical Consultant Ted Dannerth - Introduction, Electrical Preliminaries
9.26.05 Thesis Abstract Draft Submitted
9.22.05 Scrubbed Program Obtained Deloitte & Touche Space
9.19.05 Building Statistics Revisions
9.19.05 Website Revisions v0.2
9.16.05 Lighting Proposal Memo Submitted and Posted
9.16.05 Lighting Proposal Memo Draft Submitted
9.14.05 Contact Gensler Request Scrubbed Tenant Program
9.12.05 Meeting - Arch 496 Scott Wing - Professor
9.09.05 Building Statistics Draft Submitted
9.07.05 Web-Drive Mapped (T:\)
9.07.05 Website Initialization v0.1 Downloaded and Draft Running
9.02.05 Owner Permission and Thank-You's Submitted
8.23.05 Meeting - Pentagon Property Mgmt Steve Caveney - Permission Signed
8.23.05 Photographs of Interior Approx. 130 pictures
8.22.05 Meeting - A&O Tim Kehoe - Electrical, Permission Signed
8.22.05 Meeting - A/E Graphics Joe Shaw - Plan Duplication
8.22.05 Meeting - Van Buren Management Joel Lee - Developer/Owner, Permission Signed
8.22.05 Photographs of Exterior Approx. 190 pictures
8.18.05 Contact Whyte, Hirschboeck, Dudek Permission Denied
8.18.05 Contact Deloitte & Touche Permission Denied
8.17.05 Meeting - SCB Drew Ranieri and Brad Keith, Permission Signed
8.16.05 Contact A&O Permission Granted
8.16.05 Contact Gensler Informative, Permission Contingent
8.10.05 Permission Granted via phone and email
8.08.05 Building Found and Selected

 