Sears Centre Thesis Project Progression Log
Progress Log
Date | Announcement |
Current Status | Newest announcement are added to the top |
4.24.06 | Senior Thesis Complete |
4.23.06 | ABET, Course & CPEP Reflections Posted |
4.10.06 | Sears Centre Thesis Presentation |
4.3.06 | Final Report Posted |
4.2.06 | Final Report Formatted |
1.26.06 | Thesis Schedule Posted |
1.21.06 | "DBOM" Questionnaire |
1.12.06 | Updated Thesis Breadth |
1.10.06 | Contact CIMCO Refrigeration |
12.12.05 | Thesis Proposal Posted |
12.5.05 | Request Research Topics |
11.21.05 | Technical Assignment #3 Posted |
11.9.05 | Problem Identification Posted |
11.6.05 | Technical Assignment #2 Posted |
10.19.05 | Critical Industry Issues Posted |
10.12.05 | PACE Roundtable |
10.6.05 | Building Abstract Posted |
10.5.05 | Technical Assignment #1 Posted |
9.28.05 | Review Contract Exhibits |
9.27.05 | Obtain Civil Drawings and Site Layout |
9.20.05 | Resume Posted |
9.15.05 | Technical Assignment Distributed |
Information flow entered Bottom-Up (Past Reference to Most Recent)