Welcome to Tim Mueller's AE Senior Thesis e-Portfolio
Building Statistics
The FDA-CDRH Laboratory is being built on the U.S. Food and Drug Administration's White Oak Consolidation Campus In Silver Spring, Maryland. The main building is office and laboratory space with the focal area being a large high-bay laboratory on the west side of the building. It is constucted using a cast-in-place one-way concrete system with a steel framed roof. The exterior is made predominately of sheet metal, aluminum, and large glazed panels, with hoizontal sunshields.
Below is a more indepth look at what really makes up the CDRH Laboratory.
General Building Data
Building Name:
• FDA-CDRH Physics Laboratory
Location and site:
• 10903 New Hampshire Ave.
Silver Spring, Maryland 20903
Building Occupant Name:
• United States Food and Drug Administration
Occupancy or function types (type of building):
• Laboratory and office
Size (total square feet):
• 139,805 square feet
Number of stories above grade / total levels:
• Four (4) stories above grade
• One (1) ground floor below grade
• 5th floor penthouse suite
Architect, Engineers, and Contractors or CM:
• Architect: Kling in association
with RTKL
• Structural Engineer: Kling
• MEP: RTKL
• Interiors: Kling
• Site: Civil & Environmental: Greenhorne
& O’Mara
• Owner: GSA
• GC: Tompkins
Construction, subsidiary of Turner
• CM: Heerey-Tishman
• Lighting Contractor: Truland
• Mechanical Contractor:
John J. Kirlin
• Concrete Contractor: Miller
and Long
Dates of construction (start – finish):
• March 22, 2005 – November 1, 2006
Actual cost information (Overall project cost):
• $63 million
Project delivery method:
• Design-bid-build
Architecture
Architecture (design and functional components):
• The main CDRH laboratory building has a five-story central core
with the top story being reserved for the penthouse suite, and a four-story
section on the east side. The main entrance to the building is centered
on the east side while the delivery and ground level entrance is on the
north side. The below grade ground floor though the fourth floor are combined
office and laboratory space. The perimeter is mainly single offices with
the central areas being used for laboratories. There is also a large high
bay laboratory, with larger equipment including an anechoic chamber, which
is capped with a decorative curved roof on the west side of the building.
Major national model code/s:
• GSA Facilities Standards for the Public Building Service, PBS-PQ1001.1
as revised June 1996
• International Building Code, IBC 2000 (chapter 10, means of egress
excluded)
• NEFPA 101, life safety code, LSC 2000 for means of egress
• Maryland building performance standards, as amended October 2001
• Americans with Disabilities Act (ADA) and Uniform Federal Accessibility
Standards (UFSA)
Zoning:
• Zoning was not a pertinent issue for the CDRH laboratory do to the
fact that the entire property is owned by GSA. An EIS had to be done in
the beginning of the consolidation for all construction projects and needed
to be approved by the National Capital Park & Planning Commission.
Historical requirement of building or zone where built:
• The CDRH laboratory is being built on the former US Navy facility
at the Federal Research Center – Naval Ordinance Laboratory. This
site was completely cleared prior to the beginning of Phase 1 of the FDA
Consolidation; the CDRH building is part of the Phase 3 construction plan.
For historical purposes, one original building, the entrance building, will
remain on site and will be completely renovated. The new buildings will
have a style that is not traditional to the site.
Building Envelope:
• Roof: There are four levels to the roof system found at
the CDRH laboratory. The first is a planted roof that is at grade over a
section of the ground floor. It is assembled as follows: concrete deck,
water proofing membrane, protection sheet, root barrier, rigid insulation,
drainage mat, filter fabric, and soil. Also on this section is a paved roof
system that is assembled as follows: concrete deck, water proofing membrane,
protection sheet, rigid insulation, filter fabric, pedestal, and pavers.
The second level is a sheet metal roof assembly that is over the specialized
high bay laboratory space. It is assembled as follows: acoustic metal deck,
sheathing, vapor retarder, rigid insulation, “z” furring, plywood
sheeting, underlayment, and standing seam metal panel. The third roof system
is over the fourth floor, this system is termed as the main building’s
low roof and is made up an inverted roof assembly. It is assembled as follows:
metal deck, concrete deck, waterproofing membrane, protection sheet, rigid
insulation, filter fabric, and stone ballast. The fourth level is over the
penthouse suite and is termed as the main buildings high roof. It is also
made up of the inverted roof assembly.
• North Elevation: This elevation can be viewed in the rendering
below. This is the only elevation open to the ground floor. It starts out
with a solid appearance with a cast stone exterior on the ground floor.
The central section is an aluminum window curtain wall that is completely
glazing and aluminum mullions. The central area is flanked on the east by
a four-story, more traditional layout, metal panel and aluminum ribbon window
curtain wall. This wall also includes sun screens made of thin aluminum
strips placed on the upper quadrant of the windows. You can also see the
north side of the specialized laboratory space which is made by a curved
roof over an aluminum panel curtain wall. This same aluminum paneling is
used throughout the laboratory on all secondary design elements. This is
also the elevation from which you can view the vegetated retaining wall.
• East Elevation: This elevation has a large background of
the five-story central area made completely out of horizontal flush mounted
metal paneling. The background is broken up by a multitude of sunshields
on the south end of the building made to look like horizontal mullions running
half the length of the building. In the foreground of this elevation is
a three tear façade, the center of which is the most predominate
tear in which larger rectilinear sections of aluminum paneling was used.
This is flanked on both sides by an aluminum curtain wall made to have a
very horizontal feel by using a design of thin strips of the same paneling.
The final tear is made of the more traditional looking metal paneling/aluminum
ribbon window as seen in the north section.
• South Elevation: Similar to the north elevation, the south
elevation has a 5 story central area made completely out of a glazed curtain
wall with aluminum mullions. East of the central core of this is the four-story,
more traditional looking aluminum and ribbon window design with sun shields.
You can also see the lower edge of the specialized laboratory with its aluminum
curtain wall and curved sheet metal roof.
• West elevation: This is the most diverse façade,
and can also be seen in the rendering below. As with the east elevation,
the west has a broken backdrop with the north end having a formed metal
panel given a horizontal look with a waved corrugation pattern. In the foreground
of this section is once again the traditional aluminum paneling and ribbon
window curtain wall with sunshields. Below this you can see five skylights
protruding out of the green roof, to light the hallways below. On the south
end of the building is a five-story aluminum curtain wall that is completely
covered with sun shields to give an extremely horizontal feel. Also in this
section are three balconies serving the second through fourth floor. These
balconies act as a central focus point on this side of the building. With
the use of cast-in-place concrete, they are given a very rigid and enduring
look. This section also uses the same aluminum windows that are seen throughout
the building, and flush metal panels. Finally the main view of the artistic
sheet metal roof over the specialized high bay laboratory can be seen completely.
At the base of the curved roof is stone base giving it a felling of importance
and grandeur.
Primary Engineering Systems
Construction (means and methods, special systems, expanded
contract info, general items not covered in other engineering categories,
etc.):
• The construction of the CDRH laboratory had to coincide with two
other elements. One was an underground service tunnel that needed to be
knocked into once the foundation excavation was completed. The other was
a bridge that would be built to connect the laboratory to the neighboring
office building. The site is very large, thus leaving ample space for construction
trailers as well as parking for laborers and administration. Also, all roads
into the site, at the present time, are existing roads from the former functions
of the site. New road construction and traffic patterns will be managed
after the completion of this phase and do not pertain to this job. The crane
was located near the entrance to the site, making delivery of equipment
and supplies that needed to be brought in on crane very easy. The site demolition
and preparation was minimal due to the multitude of new construction occurring
on site. The building excavation included slopped sides to avoid collapse,
and a base of at least 760mm below finish grade. The entry into the excavation
pit was originally located on the north end of the building due to the grading
requirements of the finished job (the lower level is to be accessible from
the north end). Over the course of the project this hole in the excavation
will be transformed into a loading dock for supplies for construction and
then the finished building. The CDRH laboratory is also a sustainable or
“green” building and is trying to obtain a LEED rating of silver.
Electrical:
• The electrical system in all the buildings on the consolidation
site is supplied by the CUP (Central Utility Plant). There are two substations
found in the CDRH Lab, designated North and South. Each substation has 13.8KV
primary feeder from the CUP. That is converted from 3000/3990 KVA to 480Y/270V.
Due to the use as a laboratory there are many panels found in the building.
All lighting panelboards are found in closet spaces located in three positions
on each floor, North, South, and Cental. While laboratory panelboards can
be accessed from the labs and hallways for safety purposes. This building
uses both 208/120V and 480Y/270V. There are also specialty transformers
found in the building to supply many unique products such as 380Y/220V lab
equipment and specialty items such as 400Y/230V German Receptacles that
are converted using a rotary frequency converter. Typical receptacles for
the laboratory, such as duplex and 208/120V, can be found either on walls,
prefabricated raceways, or in overhead racks. Each substation services a
300KW boiler on the penthouse floor. Together the substations also service
one fire and jockey pump. The North Substation has one 1600A, 480Y/277V
busduct servicing the ground though fourth floors. The South Substation
feeds three total busducts, one 1600A, 480Y/277V busduct, and two 1000A,
480Y/277V busducts, all servicing the ground thought fourth floors. If there
is an emergency with one substation the other can take over the entire load
in order to continue operation of the lab without setback.
Lighting:
• The main luminaire used in the laboratories and offices of the CDRH
Laboratory is a linear fluorescent troffer. There is also fluorescent under-cabinet
lighting found in laboratory spaces. The typical hallway will either use
a compact fluorescent 127mm diameter downlight or a 159mm incandescent downlight.
Wallwashers found in the areas of the building are the same style as the
local downlights with a wallwashing aperture. 229mm square compact fluorescent
lights are found over cabinetry around the perimeter lab spaces. All industrial
areas such as the penthouse, utility closets, and loading areas have bare
linear fluorescent tubes. The basement lobby has a decorative “skylight”
in which linear fluorescents tubes are placed behind a translucent panel.
The actual skylights found on the ground floor have decorative lights mounted
in out coves in the concrete sidewalls of the skylight. The upper lobby
areas have linear fluorescent cove lighting housed in a decorative stainless
steel soffit. All offices, hallways, and laboratory spaces have motion detecting
occupancy censors. All lights have an emergency version that is equipped
with a battery pack incase of electrical failure. There are lit exit and
sign boxes with statements such as “laser in use” and “dark
room in use” throughout the building. The specialized high bay laboratory
has both high bay industrial 647mm fluorescent and incandescent luminaires.
The emergency lighting in this space is xenon with lead calcium batteries
around the perimeter of the room. The exterior lighting includes step fluorescents,
compact fluorescent downlights, and linear fluorescent strips in architectural
details. The sight lighting has floodlights and post top luminaries lighting
pathways and H.I.D. site pole luminaires for the surrounding areas.
Mechanical:
• Air handling units are all located in the penthouse of the CDRH
Laboratory. Air handling units 1 through 4 supply the main buildings laboratories
and offices for cooling purposes only. There are three cooling coils per
unit. Each of the units can supply 23596cfm while in taking a minimum of
14866cfm outside air. Each unit is equipped with a humidifier and an enthalpy
wheel for conservation of exhausted cooled air. They also have 30% efficient
pre-filters and 95% efficient final filters. Air handling units 5 and 6
are for the north and south stair respectively. Each unit is for heating
and cooling purposes. They can each supply 3851cfm and 4814cfm respectively
and neither need to intake any outside air. The heating for the laboratories
and offices are supplied though two electric steam boilers. The boilers
each have ten steps and a maximum of 30kw per element. They operate at a
pressure of 105KPa and have a capacity of 457Kg/HR steam. The steam is transmitted
into heat though finned tube radiation that are floor and wall mounted throughout
the building. The third floor computer room has its own chilled water cooling
unit with a capacity of 45.7KW and a supply of 3828cfm. There are nine exhaust
fans found in the penthouse, six of which are fume hood exhausts. The remaining
three are for ventilation. There are also multiple fan coil units located
in the service rooms, such as data closets and mechanical rooms. Each space
is equipped with a silencer and a VAV (variable air volume) boxes.
Structural:
• The structure of the CDRH Laboratory, with the exception of the
roofing systems, is typically made of cast-in-place concrete with a one
way slab system. Typically there are stepped footing lining the entire perimeter
of the building with a maximum step depth of 900mm. Spread footings are
located below each of the columns and were typically 6,400mm apart in the
north-south direction, with a verity of separation the east-west direction.
There is a 287KPa bearing minimum required for all footings. The ground
floor is typically either 150mm or 200mm deep slab-on-grade with150X150/MW19XMW19
W.W.F. on 200 porous fill on compacted subgrade. All the poured columns
are 600X400 in one of 6 types. With the typical column on the penthouse
being either W360X122 or W250X73. The typical joist is 254mmX520mm, while
the typical beam can range from 254mmX460mm up to 900mmX792mm. There are
also progressive collapse beams in different exterior wall sections, these
beams are typically 500mmX760mm. The steel beams in the penthouse roof range
from a W360X32.9, W310X21, W250X17.9, to a W200X15. The typical slab is
in the north-south direction with a depth ranging from 115mm to 200mm. The
loading for the building have very specific designations, however office
loading was always taken as equaling that of a corridor, for the ability
to utilize an open floor plan.
Additional Engineering and Engineering Support Systems
Plumbing:
• The CDRH laboratory has one main pump room on the ground floor of
the building. There are a total of 12 pumps. The pumps are used throughout
the building to process the multiple water and gas systems used in the lab.
There are two hot water systems, one for the labs and one for the domestic
hot water. Compressed air, vacuum, and carbon dioxide systems are utilized
in this building. There is also a deionized reverse osmosis water system
also used for supplying the laboratories. Rainwater is diverted out of the
building from the roof to a consolidation campus-wide, central storm drain
collection system.
Fire Protection (active and passive systems as appropriate.
Primary fire construction type as defined by code):
• There is an extensive fire protection plan in the CDRH laboratory,
the main fire alarm control panel (FACP) located on the first floor. This
is also the location of the annuciator panel. All floors are fed from the
FACP to a fire alarm terminal cabinet (FATC) for all of the smoke detectors
and dampers that will be used in the HVAC ductwork. Each floor also has
a power booster from which runs the strobe and speaker warning devices.
There are two standpipes found in the building, one of which also supplies
the buildings sprinkler system. A1892L/min pump brings the water to the
stand pipes. A dry pipe system is used in all areas of the building except
for the high bay area that has a pre-action sprinkler system. The high bay
laboratory does not have fire protection on its exposed structural steel.
All other exposed structural steel will receive and inorganic zinc-rich
primer. The concealed structural steel does not require fireproofing.
Transportation (elevators etc.)
• There are three elevators in the CDRH laboratory, one service and
two passenger elevators. The service elevator services all floors including
the penthouse. While the passenger elevator only services the ground though
fourth floor. The passenger elevators are hoisted with a 30KW drive and
can lift 1600 kilograms at a rate of 1.8 meters per second. The service
elevator is hoisted with a 4080 KW drive and can lift 4080 kilograms at
a rate of 1 meter per second.
Telecommunications:
• The CDRH laboratory has two data closets per floor servicing all
telecommunications on that floor. In the laboratories, telecommunications
are typically mounted below the receptacles in the prefabricated raceways
or on overhead racks. The most typical types of outlet are combination data
voice and fiber optic. The typical office’s main communication outlet
is a wall mounted combination data and voice. A few analog telephone outlets
can still be found in the break rooms. There are also some localized intercoms
between hallways and specialty rooms, such as the darkroom. The most advanced
telecommunications center is the second floor conference room. This space
includes multiple floor mounted devices, an integrated podium, overhead
speaker system, and automatic window shades.
Special Systems:
• Security: Due to the CDRH laboratory’s classification
as a governmental facility, an in-depth analysis of the security system
can not be publicly discussed. However, there are multiple cameras though
out the site connected to a CCTV system, as well all exterior and major
laboratory doors have card readers with either electric strike or magnetic
locks. There are also request to exit passive infra red motion detectors
on many of the doors.
• High Bay Laboratory: The most demanding section of the
CRDH laboratory is the High Bay laboratory. It houses very precise instruments
such as a precision calibration anechoic chamber, a controlled-environment
room (cold room), and MRI chamber. Much of the equipment is housed using
radio-frequency (RF) standalone shielding. There is also a pit section,
for the local transformers, below the basement grade to help control vibration
and interruption. Much of the power supplies had to be encapsulated as to
not allow conductivity.